S2021 Elec Planning
W21 Term Goals
Assembling final versions of boards
Motor Sense Validation (Hall-effect issues) - Weekend :)
High voltage testing
Cell balancing + BMS Testing - in progress
Validation for final versions of boards (FW & HW)
Harnessing Planning ??
Team Dependencies
Harnessing and Locations in the vehicle
Will block
Enclosures
Wiring, enclosure design, wiring, cable management have not been decided
Impacted by Dash Team
Aerobody
Blocks electrical wiring
Catamaran Box
Blocks enclosures (Rear electronics)
Hardware Working Sessions
Elec only: 9AM - 3PM on Saturdays (may be changed due to Mech, we’ll know the Wednesday of)
Can also go in during the week
Task Breakdown
Details | Goals + Timeframe | Status |
---|---|---|
Assembling final versions of boards (HW)
| Need to do more testing for lights (DRLs get hot) Determine if we have a good enough final version for each boards. (If not, we’ll put together a new rev for board sendout before the Fall term) | Current Sense: In Progress
Center ConsoleIn Progress
|
Board Validation (see tracker for validation priorities) | Charger validation → July 10th work session |
|
Telemetry | Hardware x Firmware meeting to discuss current state | Collect equipment in Waterloo, make purchases |
Motor Sense Validation (HW)
| Done as much as we can do, as of W21 | Done for now |
High voltage testing (HW)
|
| Precharge needs to be tested with motor |
Cell balancing + BMS Testing (FW)
| End of March | Medium |
Updating Firmware (FW) - Remote
| Complete before HW is assembled More detailed planning to follow |
|
Validation for final versions of boards (FW)
| End of Spring Term |
|
Solar Validation
|
|
|
Harnessing Planning
| Next term | Issues with commitment……... |
Long Term Planning
Canadian Open: June 2022
Competition: July 2022
Not feasible:
No major design changes or architectural changes
Spring 2021
Begin rear electronics integration
Begin harnessing (majority)
Begin Enclosure bring up, mounting boards
BMS, Full Mockup End of Spring
+ Charging, lights, displays Integration for mockup
+ Solar Testing
Fall 2021
Solar Integration
Integration
All Mockup Items
Telemetry
CAN Network complete
BMS Validation
How long till we can start testing with the battery pack → end of spring term (may be able to test w/ cells on the bench, but we’ll want to test with the BMS with battery before integration with mech)
BPS Scrutineering Mock-test
Winter 2022
Testing
Spring 2022 (May)
Testing for competition
Topics of Discussion:
Key Milestones
BMS Mockup
Full Mockup
Charging, Lights
Solar
Testing
Integration
Other Projects Post-Completion