Firmware Validation Plans F20

Timeline planning spreadsheet link: https://docs.google.com/spreadsheets/d/14eVjn5qeHOSkJxxsRyDxVjPF8R5smcw8_9Mv0pXNogo/edit#gid=33976054

General Plan:

Simple Validation Smoke Tests

Start Date

End Date

Notes

Center Console

Sep 20, 2020

Sep 26, 2020

Firmware updates required.
Hazard lights, DRL toggle, LED lights support, I/O expander.

Steering Stalk

Sep 8, 2020

Sep 10, 2020

 

Pedal Board

Sep 8, 2020

Sep 10, 2020

 

Motor Controller Interface

Sep 10, 2020

Sep 13, 2020

MCI testing needs to be offboarded to Jess, make sure CAN adapter properly configured to see if it's a hardware issue
4 day window (need HW support to set up MCI)

Charger

 

 

Not a priority, to validate after elec mockup

Power Selection

 

 

 

 

 

 

 

Complex Validation

Start Date

End Date

 

Power Distribution

Sep 14, 2020

Sep 16, 2020

Staggered because not enough hands

BMS Carrier

Sep 14, 2020

Sep 20, 2020

 

Solar

 

 

Not assembled yet