Firmware Validation Plans F20
Timeline planning spreadsheet link: https://docs.google.com/spreadsheets/d/14eVjn5qeHOSkJxxsRyDxVjPF8R5smcw8_9Mv0pXNogo/edit#gid=33976054
General Plan:
Simple Validation Smoke Tests | Start Date | End Date | Notes |
Center Console | Sep 20, 2020 | Sep 26, 2020 | Firmware updates required. |
Steering Stalk | Sep 8, 2020 | Sep 10, 2020 |
|
Pedal Board | Sep 8, 2020 | Sep 10, 2020 |
|
Motor Controller Interface | Sep 10, 2020 | Sep 13, 2020 | MCI testing needs to be offboarded to Jess, make sure CAN adapter properly configured to see if it's a hardware issue |
Charger |
|
| Not a priority, to validate after elec mockup |
Power Selection |
|
|
|
|
|
|
|
Complex Validation | Start Date | End Date |
|
Power Distribution | Sep 14, 2020 | Sep 16, 2020 | Staggered because not enough hands |
BMS Carrier | Sep 14, 2020 | Sep 20, 2020 |
|
Solar |
|
| Not assembled yet |