2020-02-21 - Solar + PD + Timelines

Aashmika:

-can finish fixes by the end of weekend

-sendout monday - give gerber zip to micah

-send to Ontario manufacturer

 

Josh:

-general front PD edits

-document loads for front pd with voltages

-sendout monday - give gerber zip to micah

 

Liam:

-can pi get shutdown from uart ? ask arshan as well

 

Manufacturing:

-candor pcb manufacturing - for rest of fabs

 

Timelines:

-James and max have to work on the electrical schematic setup - after diagram is complete

-mockup for electrical finalized for feb 29th - Aashmika

-standardized sizes for wire gauges (high power high current, high current, signal wires, board power, power from DCDC to power distribution (12)) - mid next week

-schematic for lights done on 29th - Aashmika & Micah

-sendout for DCDC, rear power, contact sense, lights, steering interface - march 14th

-send out redesigns for testing of bms and precharge - march 21st