Interiors S2021 Planning

This document outlines the tasks for the Interiors team for the Spring 2021 term.

Term Goals

Project

Goal

OG Date

Date (March)

Priority

Project

Goal

OG Date

Date (March)

Priority

Catamaran Cover

Complete manufacturing

3 months

End of May

3 months

End of Sep

High

Seats

Complete manufacturing (plan https://docs.google.com/document/d/1t6-ZhpMnQ-8Mp0LCcsmOvhaA2A8u8Zm8mg8Jn0yAIVg/edit# )

  • testing to confirm design

  • start seat pan manufacturing

  • weld brackets to the chassis

2 months
End of April

2 Months

F21

 

High

Doors

Complete FULL manufacturing plan (EOT W21)

  • Hinges and Latch need access to A-Plane

  • Latch & Hinges components (2w)

  • Molds & Composites

    • Need manufacturing plan

    • Manufacturing time

** Any Structures changes to hinges need to be communicated

2 months
End of February

Manufacturing Time: 2 months

Commitment for Manufacturing Completion: Mid-F21

High

Trim

Complete detailed design
Started manufacturing plan

  • Currently figuring out headliner

4 months
Fall Term

Trim Integration: 2 months

Medium

Dashboard

Complete detailed design
Started manufacturing plan

4 months
Detailed design & Completed Manufacturing Plan: Mid-S21

 

Manufacturing: 3 months

Integration: 1-2 months

High

 

Manufacturing Projects

Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. VDR is in progress for seats (~85% completed).

Project

Task

Time Allocation

Status

Project

Task

Time Allocation

Status

Catamaran Cover + Seats

Obtain all materials required for manufacturing the catamaran cover
(MDF, layup consumables)

Finish assembly plan

BOT

In PRogress

All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT

Catamaran Cover

Manufacture Molds

  • Cut and glue MDF

  • Machine molds

  • Sand and prime

2 weeks

Not Started

 

Manufacture Major Battery Box Panels (bottom + side walls + lid)

  • Prep work

  • Make extra for test specimens

3 weeks

Not Started

 

Manufacture Internal Parts
• 3D printing
• Cutting and thermoforming polycarbonate

1 week

in progress

 

Material Testing

  • Deflection test

  • Heat test

  • Adhesive test

1 week

Not Started

 

Dry Run Assembly with Electronics

• Install electronics and battery modules

• Mark part locations

• Test fit catamaran cover into car

→ Will gate electrical

1 week

Not Started

  • will require coordination of finished chassis, bottom panel, battery modules

 

Final Assembly
• Epoxy internal components
• Install electricals

• Permanent mounting of catamaran cover to chassis

2 weeks

Not Started

 

External Finish
• Add fabrics and other cosmetic trim to battery box Nice to Have

TBD

Not Started

Seats

Seats Mock-up (optional)
• Fabricate and install flat panels in wood to verify seating position, harness pass-thru, visibility, steering wheel and pedal position
• May need to mock-up seatback using flat sheets

1 week

DONE

Manufacture Seats Flat Panels using the Glass panel

  • Fabricate all seat pan flat panels in carbon fibre (either in 1 go or 2 depending on the size of vacuum bag)

  • Bond flat panels to bottom panel/structural elements

2 weeks

Not Started

Manufacture seat supports

  • depending on method chosen:

    • 2 built in filets (require small amount of mdf and require producing each seat support separately which is time consuming considering there are 8 of them)

    • 1 built in filet (require producing each seat support separately which is time consuming considering there are 8 of them)

    • 0 built in filets (will be weaker around 1.5-3 times based on research but can manufacture flat pieces 4 supports at a time meaning there will only be 2 rounds of infusion)

2 filets 3 weeks

1 filet 2-3 weeks

0 filets 1 week

Not Started

Ballast using using the Glass panel

  • after install of seat pan the measurements and checking to make sure the ballast will hold enough weight/there will enough room

  • begin manufacturing flat panels (glass sheet)

  • install with hinges, lock, and lid

2 weeks

Not Started

Brackets and fastener installation

  • order brackets (if VDR approved)

  • order bigheads

  • order fuji/flex locks

  • drill appropriate holes and weld brackets onto chassis

3 weeks

Not Started

  • Further purchases are required (brackets approved by EngSoc)

  • fasteners TBD

Manufacture Seatbacks
• Fabricate tooling for non-flat panels (mdf)
• Fabricate non-flat seatback panels
• Install seatbacks into car

2 weeks + 1 week = 3 weeks

Not Started

 

Finishing Touches
• Fabricate foam padding and cushions and install
• Fabricate and install remaining fabric coverings
• Install harnesses

TBD

Not Started

  • These can be done over long term

  • Further purchases are required: fabric

Integration with Subteams/Dependencies

  • Catamaran depends on:

    • Aero-chassis BP integration

    • Battery box modules ready

    • Dynamics assembly

  • Seats depends on:

    • Chassis integration

    • Side panel integration (for rear seats install)

    • Floor panels SHOULD NOT need to be added into the vehicle (so that brackets can be welded)

    • Welding items for chassis

    • B,C-bulkheads Integrated

  • Dashboard depends on:

    • Dynamics

    • Aero-Chassis Integration (A-bulkhead, A-Plane)

    • Interior doors

    • Electrical & Battery Box need to be integrated so we can route wires

      • Depends on Displays & cameras to be ready

Contingency Planning

  • If lockdown happens, manufacturing will be impacted as long as lockdown remains

Design Projects (Trim + Dashboard)

Task

Time Allocation

Status

Task

Time Allocation

Status

Finalize Research + Concepting

2 weeks

In PRogress

CAD design

4 weeks

In PRogress

Materials Selection

2 weeks

In PRogress

Supplier Interfacing

Assembly Plan

TBD

Not Started

 

Core Team

Name (Term)

Responsibilities

On-site Capacity

Name (Term)

Responsibilities

On-site Capacity

Renzo (Co-op)

• Leading manufacturing of catamaran cover
• Form factoring of dashboard

On-site

Sheila (School)

• Leading manufacturing of seats

On-site

Ali (School)

•Design and integration of Dash

On-site

Cordelia (School)

• PM for dashboard
• PM for seats

On-site

Asher (Co-op)

• Leading manufacturing of seats

Remote

Kimia (School)

• Design of ballast

On-site

Lovisa (Co-op)

• PM of trim

Remote

Jens (School)

  • Trim

On-site

Joy ()

  • Dashboard

On-site