Interiors S2021 Planning
This document outlines the tasks for the Interiors team for the Spring 2021 term.
Term Goals
Project | Goal | OG Date | Date (March) | Priority |
---|---|---|---|---|
Catamaran Cover | Complete manufacturing | 3 months End of May | 3 months End of Sep | High |
Seats | Complete manufacturing (plan https://docs.google.com/document/d/1t6-ZhpMnQ-8Mp0LCcsmOvhaA2A8u8Zm8mg8Jn0yAIVg/edit# )
| 2 months | 2 Months F21
| High |
Doors | Complete FULL manufacturing plan (EOT W21)
** Any Structures changes to hinges need to be communicated | 2 months | Manufacturing Time: 2 months Commitment for Manufacturing Completion: Mid-F21 | High |
Trim | Complete detailed design
| 4 months Trim Integration: 2 months | Medium | |
Dashboard | Complete detailed design | 4 months
Manufacturing: 3 months Integration: 1-2 months | High |
Manufacturing Projects
Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. VDR is in progress for seats (~85% completed).
Project | Task | Time Allocation | Status |
---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT | In PRogress All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT |
Catamaran Cover | Manufacture Molds
| 2 weeks | Not Started |
| Manufacture Major Battery Box Panels (bottom + side walls + lid)
| 3 weeks | Not Started |
| Manufacture Internal Parts | 1 week | in progress |
| Material Testing
| 1 week | Not Started |
| Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week | Not Started
|
| Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks | Not Started |
| External Finish | TBD | Not Started |
Seats | Seats Mock-up (optional) | 1 week | DONE |
Manufacture Seats Flat Panels using the Glass panel
| 2 weeks | Not Started | |
Manufacture seat supports
| 2 filets 3 weeks 1 filet 2-3 weeks 0 filets 1 week | Not Started | |
Ballast using using the Glass panel
| 2 weeks | Not Started | |
Brackets and fastener installation
| 3 weeks | Not Started
| |
Manufacture Seatbacks | 2 weeks + 1 week = 3 weeks | Not Started
| |
Finishing Touches | TBD | Not Started
|
Integration with Subteams/Dependencies
Catamaran depends on:
Aero-chassis BP integration
Battery box modules ready
Dynamics assembly
Seats depends on:
Chassis integration
Side panel integration (for rear seats install)
Floor panels SHOULD NOT need to be added into the vehicle (so that brackets can be welded)
Welding items for chassis
B,C-bulkheads Integrated
Dashboard depends on:
Dynamics
Aero-Chassis Integration (A-bulkhead, A-Plane)
Interior doors
Electrical & Battery Box need to be integrated so we can route wires
Depends on Displays & cameras to be ready
Contingency Planning
If lockdown happens, manufacturing will be impacted as long as lockdown remains
Design Projects (Trim + Dashboard)
Task | Time Allocation | Status |
---|---|---|
Finalize Research + Concepting | 2 weeks | In PRogress |
CAD design | 4 weeks | In PRogress |
Materials Selection | 2 weeks | In PRogress |
Supplier Interfacing Assembly Plan | TBD | Not Started |
Core Team
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (Co-op) | • Leading manufacturing of catamaran cover | On-site |
Sheila (School) | • Leading manufacturing of seats | On-site |
Ali (School) | •Design and integration of Dash | On-site |
Cordelia (School) | • PM for dashboard | On-site |
Asher (Co-op) | • Leading manufacturing of seats | Remote |
Kimia (School) | • Design of ballast | On-site |
Lovisa (Co-op) | • PM of trim | Remote |
Jens (School) |
| On-site |
Joy () |
| On-site |
Onboarding Project
Onboarding Project Instructions