2020-06-06: Dynamics Stand-Up

  • Bellcrank is currently a wildcard and not taken. If not taken by the end of the week, Kevin will be completing the design.

  • Bellcrank clevis is currently in the MVP stage. This could be a task for members that are currently Shadows to the DRI new tasks.

  • FEA done, weight optimization cld be done, ready for supplier interfacing

  • AJ & Leif will be having a design review for Shock Clevis today (currently in the MVP stage)

  • Brake Caliper Mount - FEA review at 2:30 pm

  • Design review needed for the whole wheel assembly (June 8 or 9)

  • Kevin and Leif - General Handoff of parts needed

  • Design Review (June 8/9): Spindle, Spacers, Rims, Hubs

  • Update on UCA Housing - Safety Factor of 8 derived from FEA