Lights Timeline + Tasks
Phase 1: Research + Preliminary Ideas
Task | Assigned To | Date to be done |
---|---|---|
General Light’s Research
| Everyone | End of February |
LED Projection
|
| End of February |
Manufacturing and Integration into Aerobody
|
| End of February |
Phase 2: Design
Task | Assigned To | Date to be done |
---|---|---|
Covers
|
| March 27, 2023 |
Full Headlight Assembly + Confirm with Hardware |
| March 27, 2023 |
Headlight Mold For Thermoforming |
| March 27, 2023 |
Phase 3: Prototyping + Manufacturing
Task | Assigned To | Date to be Done |
---|---|---|
3D Printed Headlights Prototype |
|
|
MDF Mold | Jasmine & Graeme |
|
3D Printed Final Parts |
|
|
Thermoformed Cover |
| EOT we have up to this stage done |
Full assembly with PCB’S |
|
|
Integration into AEROBODY |
|
|
Review March 9 Update:
Great research on meeting angles (potential solutions - Ryan and Fatima’s research), potential problems/solutions of over heating
Next step: research for manufacturing and integration into the aerobody, back cap design introduced, next review headlight assembly designs