2019 FSGP Planning Meeting
Key Dates
Date | Event |
---|---|
May 6 | First day of the term |
May - June | Testing the car |
End of June | Packing the car |
End of June | Driving to Austin |
July 1 - July 3 | Scrutineering |
July 4 - July 6 | Racing |
Changes to MSXII since 2018 ASC
Electrical Systems
Which electrical systems have changed since the ASC?
- Driver Controls
- BMS AFE
- Pre-charge
- EV Charging
- Telemetry System?
- Firmware Changes?
Mechanical Systems
What changes to the mechanical systems that we should be aware of?
- Interior?
- Charging port?
Validations
The status of the projects that we want to use in 2019 FSGP
Project | Status | To-Dos |
---|---|---|
Driver Controls | ||
BMS AFE | ||
Pre-Charge | ||
EV Charging |
Backup Boards and Components
- Which boards do we need to bring up before the competition?
- Breakout board
- Controller board
Checklist
What do we need to check off before the ASC
Tests
Track Tests
- Few track tests before the ASC?
Bench Tests
- Testing the readiness of the electrical system in the bay
Other Projects in Spring 2019
Continue from Winter 2019
- What projects are we going to continue in the spring
New Projects
- Which projects are we going to start in 2019