Electrical
Firmware:
FIRMWARE COOP W25: Interviews Dec 3-5. Release rankings by Dec 5 at 8 PM.
Flashing and GPIO’s work on the new controller board! But RTOS is broken Will be fixed today
Published Doxygen Website for Firmware Code Documentation
Mechanical
W25 Internal Structures Coop → Interviews start Dec 5-7
EOT Design Reviews: Dec 19th-Dec 23th
Rear Hub → select design, drawings ready by Jan 6th
Detachable steering → if design ready, parts will be order over Christmas break
MS16 Developments up to now
MS15.5 VDR revisions over the break
Exteriors Term Wrap-up:
…
Internal Term Wrap-up:
MS15.5 Chassis Resim update
Battery Term Wrap-up:
…
Dynamics Term Wrap-up:
Parking Brake Rehaul BOM due Dec 13th
FSU: Calculator completed, FSU team will lock down nodal after finals
Steering: Loading calculator started, will be complete before Dec 13th, and will lock over-top and middle nodal before w2025
Operations
Other