Controller Board
...
Project Validation
Project | Status | Blockers |
---|
CAN
- Loop back mode Mitchell Langdon Ostler
- External Controller (Peak CAN) Jarvis Weng
- Controller Board to Controller Board Jarvis Weng
Completion Date | ||
---|---|---|
|
title | In Progress |
---|
GPIO_IT
- General Hardware Verification Preston Glicerio Dresser
Status | ||
---|---|---|
|
ADC
- General Hardware Verification Mitchell Langdon Ostler
| |||||||
|
|
I2C
- General Hardware Verification Adel Chinoy
Status | ||
---|---|---|
|
SPI
- General Hardware verification
| Final PRs merged, New Hardware in transit | |||
|
|
Need SPI sensor to test further
Power Distribution
Validation Steps
Status
Blockers
Outputs
- Verify Operation of IO expanders using smoke test Adhiraj Singh Arvind Sanjay
- Verify Operation of Load switches using bts_load_switch driver
- Verify Operation of Outputs using Output Config
Status | ||
---|---|---|
|
Need output config merged for last verification
Fan Controllers
- Develop Smoke Test
- General hardware verification of Fan Controllers
Status | ||
---|---|---|
|
Output Read verification
- Verify Outputs are successfully read in main loop
| |||||||||
| Make a new smoke project for this | ||||||||
| Continue validation steps | ||||||||
|
|
| Need |
Lights FSM verification
- Verify by setting can messages internally
- Verify by sending can messages over PEAK CAN
to push in PR | ||||
|
|
| Need |
Power FSM Verification
- Verify by setting can messages internally
- Verify by sending can messages over PEAK CAN
to review to PR | ||||
|
|
Need all previous verified
Telemetry
...
Validation Steps
...
Status
...
Blockers
...
HC-12
...
- Develop basic tooling and verify connection/data transfer
...
Status | ||
---|---|---|
|
...
Getting hardware
...
LoFa
...
- Develop basic tooling and verify connection/data transfer
...
UV Cutoff
Validation Steps
Status
Blockers
Load Switch
- Check that load switches work, and isense can be read
Status | ||
---|---|---|
|
VBAT_Status
| |||||||||
| Some are broken again….. |