  1. Electrical

    1. HW weekly update: everyone who finished onboarding is working on something now, main projects: BMS (AFEs for new members, Aden+Jun carrier), solar (to be testing, maybe solar sense, rn new members learn about solar), Controller Board breakouts, Driver Controls + Backup Camera. Todo in the near future: harnessing, soldering session

    2. Going to schedule a time for Solar/MPPT testing to diagnose ongoing solar issues.

    3. FW weekly update: ~10-15 ppl have finished onboarding and have been assigned tasks.
      Telemetry is being worked on—issues with UART driver. Aryan will fix it today. We may need to purchase more XBees due to a version mismatch between our ones. If not completed by the end of October, Aryan will help finish it.

  1. Mechanical

    1. General

      1. MS15 → make car that drives, MS16 → make car that is reliable (and perform good)

      2. Documentation WIP:

        • Design - Best Practices, Bild - Rules & Tutorial, Bay Rules - Around the solar car, Companies/ Services of Interest

      3. Space Claim #3

        • Suspension finalize space allocation, figure out steering spot, place battery to balance CG

      4. Jira is live, please use it

      5. Working with sponsors/ sponsorship teams?

    2. Exteriors

      1. Weekly Update

    3. Battery

      1. Weekly Update

    4. Internal Structures

      1. Onboarding

        • Some members almost done, moving them onto MS15.5 interiors tasks/design sprints

      2. Occupant Cell → Ethan = 🐐

        • Running the first round of Sims for rollcage

        • Reaching out to people to figure out more optimized solutions

      3. Dynamics Framing

        • Flushed out the first round of dynamics mounting tubes

      4. Aero-chassis integration

        • Will reach out to aero team a little later on in the week

      5. Weekly Update

    5. Dynamics

      1. Suspension

        • Parametric Nodal Checkpoint: End of Hell Week

        • Finalize Plan with Rear Hub: Before Reading week

        • Weekly Update

      2. Steering

        • Parametric Nodal Checkpoint: End of Hell Week

        • Weekly Update

      3. Brakes

        • Calculator Checkpoint: End of October

        • Total cost breakdown of MS15 brake components

        • Limit switch/ rotary encoder discussion

        • Weekly Update

  1. Operations

  2. Other

    1. Midsun Resume Review?