These are the firmware projects we will be working on for the next 4-8 months. If you are new to the team or interested in any of these projects, contact the project owner. If a project does not have an owner, feel free to take it on !
Project | Tasks | Estimated Duration | Priority | Owner |
---|
Driver Controls | - Regenenaraive braking
- Mech brake sensor stability
- Implementing firmware changes to match the new boards
-
ELEC-549
-
Getting issue details...
STATUS
| 1.5 months | Highest | Andy |
Driver Display | - Validation and integration
- light sensor
-
ELEC-434
-
Getting issue details...
STATUS
| 2-3 weeks | High | Andy |
Battery Management System | - State of charge algorithm
- AFE's need to be reconfigured
- Cell balancing
- Thermistor array
-
ELEC-540
-
Getting issue details...
STATUS
| 2 months | High | Ash Nicholas (SoC) |
Motor Interface Board | - Needs to be validated
- Ensure that critical messages are being received
-
ELEC-530
-
Getting issue details...
STATUS
| 2-3 weeks | Highest | Ash, Calder, Misha |
Telemetry | | 1-2 months | Medium | Calder Jennifer Aaron |
Board validation | - Program the new boards and create tests for them
| 2-3 weeks | Low | Alex G. |
Solar Sense | - Ensure that the relays work correctly
-
ELEC-554
-
Getting issue details...
STATUS
| 2-3 weeks | High | Misha, Ali |
IMU Board | - Write application layer code for board to communicate with telemetry
- Consider logging straight to SD card
-
ELEC-63
-
Getting issue details...
STATUS
| 2-3 Weeks (Driver) 2 Weeks (Application) | Medium | Marwan R, Alex F, Patrick M, Cathy L |
GPS Board | - Finish writing the GPS driver for the telemetry board
-
ELEC-71
-
Getting issue details...
STATUS
| 2 weeks | Medium | Misha |
Infrastructure | - Optimize x86 abstraction layer
- Codegen auto rolling bot
| 1 month | Low |
|