Skip to end of metadata
Go to start of metadata

You are viewing an old version of this content. View the current version.

Compare with Current View Version History

« Previous Version 3 Next »

  1. Mechanical

    1. Dynamics

      1. Rear hub and spindle finished by early March?

      2. Does E3 have 5 axis CNC’s?

    2. Internal Structures

      1. Occupant cell mockup completed - a little worried about space for egress so some changes might be needed for space claim (will discuss on Monday)

      2. supplier reach out starting this month

        1. what’s this process looking like w/ sponsorships?

      3. Ian finished a first edition of rollcage jig, pending review

  2. Electrical

    1. PCBs have arrived, will continue on assembly/integration this coming week

    2. Slowly starting to assign/plan projects for MS16, will be assigning

    3. Hopefully lock down/finalise further MS16 electrical architecture

  3. Operations

    1. EngSoc funding submitted

    2. WEEF Funding due next week - operations members will be working on the presentation throughout next week

    3. Form for preferred hoodie design WIP in #general channel

      1. Possible re-design to account for aerobody render for MS16

  • No labels