Battery Box Workflow

Project Deadline

Project

Fall 2023 Sub-Tasks

Deadline

Assignee

Notes

Aux Battery

Finish CAD - Sept 24
Prototype Module - Oct 1
Aux Design Freeze - Oct 17
One module fully tested and complete - Oct 20
Aux Enclosure Manufactured - Oct 31
All manufactured - Nov 21

November 30, 2023

Jenna

Status:

Design: Done

Reivsion: Current

Manufacturing:

Battery

Manufacturing process draft - oct 7

List of hardware - oct 7

Terminal Covers - Done

All modules manufactured - Nov 30

November 30, 2023

Donna

Status:

Design: Completed (10-2023)

Manufacturing: In progress

BMS

Colomb counting

N/A

HW + FW
Eric + Kostubh

SoC Estimation

Enclosure

Manufacturing Timeline:

https://docs.google.com/spreadsheets/d/1QArUINVpH-BzhHEo5_4B9GzHI4H_3hRY4KuvtRcqRTk/edit?usp=sharing

November 30, 2023

Shem + Nicole

Design - Locked

Manufacturing - In Progress

PVDR/VDR

Draft Completed → Sept 23

Testing: TBA

September 30, 2023

Owen

Draft - done

Due: Novemeber 5

Tasks To-Do