Weekly Goals
Week | End of Week Goals | Notes |
---|
July 5 - 11 | Chassis: (All done!) Access to Welding Room Finish sanding & assembling jigs (done) Drop off parts for welding Assembly more jigs Welding components onto Chassis
Aero: (Bleeding into week of July 12 - due to booking conflicts with Waterloop) Battery Box: | |
July 12 - 18 | Chassis: Pick up waterjet parts - End of the week Sand chassis, assemble more jigs
Schedule welding in E5 - welding components onto Chassis
Aero: Finish prepping side panel molds - end of the week
Begin material prep for side panels layup
Make a decision if we want to layup both - yes to both
finish side panel molds 3, 4
b bulkheads sand, potentially make blank and machine second mold as well (based on SDC)
Composites: | |
July 19 - 25 | Chassis: Aero: Composites: Battery Box: Purchases: | |
July 26 - Aug 1 | Chassis: Aero: Cure & Demold L. Side panel Finish sanding R. Side Panel 3,4 molds Organize prepreg in the freezer Make material list for 2nd Side Panel B-Bulkhead
Composites (Infusion): Testing the Glass: Test #1: Pull vacuum on glass to see if it can hold vacuum (Monday/Tuesday) Test #2: use wax/grease remover for glass midweek and pull vacuum (Wednesday/Thursday) Test #3: Flip glass to test on other side and pull vacuum (End of Week)
Obtain inlet & clamps from Brian Infusion Test: Material Prep for test piece (before Saturday) Saturday July 31st: Run Resin through part
| Side panels: #3 almost done #4 up to 600
Purchases to be made: |
| | |
Instructions: Please fill this out BEFORE the onsite check-ins
Date | Individual | Goals for Today | Progress / Updates |
---|
| Micah Black | | Continued Battery Spot Welding |
July 8, 2021 | Mackenzie Lui, Kyle Lacson | Transport excess material to cold storage facility, set up paint guns. | Paint guns |
| | | |
| | | |
| | | |
| | | |
| | | |