This page will outline the roles and responsibilities + action plan for the Spring '21 term!

Agenda

  • Figure out how people can maximize the amount of on-site work (take things home, go into bay, what they can accomplish)

  • Figure out all tasks that can be delegated + how can we make them so that those people can help the onsite team (creating BOMs, Digikey, test plans)

  • Role shifts / assignments --> onsite vs. offsite leads (onboarding), who needs support where people take stuff done but end up blocked or can’t --> how to minimize that, how to achieve the mental state to push or ask for support --> will people be more motivated if given more responsibilities?

Term Goals

No specific dates since COVID might just screw everything up… will use time estimates 😢

Details

Priority

Timeline

Assembling final versions of boards

  • PD, Lights, Steering, Solar, UV Cutoff, BMS Carrier

HIGH

4 months

Final designs for boards (for sendoff by EOT)

  • Pedal, Precharge, UV Cuttoff?, Solar?

HIGH

4 months

Complete wiring diagram

  • Make the importance of the tasks more clear (smile)

  • Aren’t too far from completion

HIGH

End of June

MANDATORY WORK SESSIONS 😤

Finalize enclosure layouts

  • Feedback for interiors

MEDIUM

dependent on Interiors

Validation / Testing

  • Powertrain, MCI

  • Charger Interface

    • Elcon Charger to mockup battery

  • Precharge

  • BMS

    • Connect power supply to each channel, verify lower and upper faults

  • Solar Sense → can test outside (tongue) (MPPT layout)

  • Don’t have a load to test motors… Need to put it on the car

MEDIUM

Further testing motors depends on mech (need rolling chassis)

BMS → dependent on battery, also need BMS Carrier assembled

HV integration into mockup

LOW

Telemetry, Headlights and Cameras (w/ Interiors)

LOW

Sorry, Renzo

Carryover from Fall 2020

Carryover from Winter 2021

All onsite tasks:

  • Assembling final versions of boards (HW)

    • PD

    • PS (done)

    • Steering

    • Lights

    • Solar

    • UV Cutoff

    • Centre Console (done)

    • Current Sense (done)

  • Motor Sense Validation (HW)

    • At the stage of integrating Sense to Controllers

    • Blocks all of Power Train

  • High voltage testing (HW)

    • Integration Testing

    • Blocked by Motor Sense Validation

    • Blocked by Pre-Charge integration testing

  • Assemble final versions of most boards (excl. AFE, DCDC, Charger interface, MCI) (January)

    • HW validation for new versions

    • Notes:

      • Aashmika has the reflow at home to assemble most boards

      • if lockdown happens, this can still be done at Aashmika’s house.

    • Unit test boards once they return

      • if designs are flawed, board needs to be resent (at any stage)

  • Integrate into mockup (February) - must be onsite

    • Displays

    • Horn

    • Cameras

    • Telemetry Router

  • Mockup Testing

    • Solar

    • BMS Full (Pending Battery pack, and other testing)

    • MCI, Limit testing for Motors (includes carryover from F2020)

    • Full Mockup Integration (w/ displays)

    • Worst case: bleed into Spring

  • Complete all harnessing/make diagram for full vehicle (near EOT)

    • Includes layout

    • Note: this is offsite, if lockdown, will move this task to Jan

  • Finalize Enclosures Layout
    (to plan for post W2021)

Spring Term

  • Assembling Final Versions of Boards

  • Complete all board mounts

  • Complete all harnesses

  • Complete all enclosures

  • Assemble all items

See full documentation here

Core Team

Name (Term)

Responsibilities

On-Site Capacity

Aashmika (School)

• Assembly of final versions of boards
• Precharge

• Onsite
• Available on most weekends
• Can possibly take some boards home to work on, during the week

Micah
(School)

• Motor sense validation
• Enclosures finalization

• On site, focus on battery box (1 month)
• Part-time + 3A… 😅

James L
(Co-op)

• Assembly of final versions of boards
• Telemetry Diagram

• Remote, will in in-person in Fall 2021
• Most likely can’t help

Nita
(School)

• Assemble PD (reflowed on side, hand-assembled the other side)
• Task force for diagram making

• Remote
• Can maybe visit on weekends but will be overloading during the term

Liam
(School)

• Assembly of final versions of boards

• Remote
• has equipment to do assembly / validation without being in loo

Kristen
(School)

• Harnesses?

• On Site
• Grunt work (smile) that requires limited hardware knowledge

Ricky
(Co-op)

• Onboarding?

• Onboarding 😃

Returning Members

  • Remote Members: Ricky Huang, Janvi, Alastair, Lucy

  • On-Site Members: Odianosen, Vinai, Hunter

Onboarding

Knowledge Share

Lead

Date

Week 1

Aashmika

Week 2

Nita

Week 3

James

Week 4

Ricky

  • Goal for this term

    • a dummy’s intro to the electrical sub-systems 2.0

  • Previous onboarding

    • a dummy’s intro to the electrical sub-systems

    • design a board

    • how to be useful onsite

  • Engagement ideas (after members watch videos)

    • Jump on a call to do worksheets together

    • Kahoot

Purchases

Item(s)

Estimate Price

Source

board sendout (midterm)

WEEF W2021

infotainment screen

ENGSOC W21

Maha Batteries (Battery Box?)

WEEF F2020

Label maker

WEEF F2020

Pick and Place ($11k) → Neoden?

  • $3000 for certifications (apply for more funding)

  • + tax + import fees + USD + shipping 😞

  • SSDC doesn’t like aliexpress 😞

WEEF W2021

Tasks for Off-site Members

Task

Difficulty

Notes

Power Consumption Evaluation

MODERATE

Wiring Diagram

MODERATE

Component Investigations

EASY / MANAGEABLE

  • Reviews for all tasks together (smile)

    • Last Saturday of each month? Extended standup 😞

  • Buddy system (2-3 members w/ a lead)

    • Leads combine tasks to have groups work on them together (Kristen (smile))

    • Saturday work sessions

    • Standups once a week → Wednesdays

Expectations for Next Term

  • RETAIN MEMBERS 😃

  • Join On-Site weekly standups to get a better grasp of overall elec progress, improve knowledge

Next Steps

Term Layout - Remote Tasks

  • Wednesday standup to go over group progress - groups will give updates together

  • Saturday working sessions where everyone works together on discord and can separate into channels for specific questions

  • Everyone will take ownership of the groups task and hopefully will help with motivation to get things done

Groups

Leads to work with or ask if you have any questions

Group Name

Lead

Members

Start of term tasks

Group 1

Aashmika

  • Ricky

  • Frank

  • Kevin Lee

  • Tanish

  • power consumption 1

  • mockup diagram 1

  • component investigation 1

  • Pick and Place

Group 2

Nita

  • Lucy

  • Renee

  • Odi

  • power consumption 2

  • mockup diagram 2

  • controller board testing PCB

Group 3

Micah

  • Ivan

  • Shanika

  • Ricky Li

  • power consumption 3

  • mockup diagram 3

  • ESD protection methods

Group 4

Liam

  • Alastair

  • Vinai

  • Kevin Li

  • power consumption 4

  • mockup diagram 4

  • component investigation 2

Group 5

James

  • Hunter

  • Janvi

  • Matthew

  • power consumption 5

  • mockup diagram 5

  • component investigation 3