Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 7 Next »

This document outlines the tasks for the Interiors team for the Winter 2021 term.

Term Goals

Project

Goal

OG Date

Date (March)

Priority

Catamaran Cover

Complete manufacturing

2 months
End of February

2 months

End of April

HIGH

Seats

Complete manufacturing

  • mockup needs to be done as early as possible for any changes for manufacturing

2 months
End of April

2 Months

HIGH

Doors

Complete manufacturing plan

** Any Structures changes to hinges need to be communicated

2 months
End of February

2 Months

HIGH

Trim

Complete detailed design
Started manufacturing plan

4 months
End of April

MEDIUM

Dashboard

Complete detailed design
Started manufacturing plan

4 months
End of April

MEDIUM

Displays

Ensure Infotainment display works
Complete design of Driver Display
Wires for strategy dashboard
Wires for telemetry dashboard

2 months
End of February

4 months

End of April

LOW

“easiest”

Manufacturing Projects

Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. Strongly recommend we do this asap so that we don’t run into problems when it’s too late.

Project

Task

Time Allocation

Status

Catamaran Cover + Seats

Obtain all materials required for manufacturing the catamaran cover
(MDF, layup consumables)

Finish assembly plan

BOT

IN PROGRESS

All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT

Catamaran Cover

Manufacture Molds

  • Cut and glue MDF

  • Machine molds

  • Sand and prime

2 weeks

NOT STARTED

Manufacture Major Battery Box Panels (bottom + side walls + lid)

  • Prep work

  • Make extra for test specimens

3 weeks

NOT STARTED

Manufacture Internal Parts
• 3D printing
• Cutting and thermoforming polycarbonate

1 week

IN PROGRESS

Material Testing

  • Deflection test

  • Heat test

  • Adhesive test

1 week

NOT STARTED

Dry Run Assembly with Electronics

• Install electronics and battery modules

• Mark part locations

• Test fit catamaran cover into car

→ Will gate electrical

1 week

NOT STARTED

Final Assembly
• Epoxy internal components
• Install electricals

• Permanent mounting of catamaran cover to chassis

2 weeks

NOT STARTED

External Finish
• Add fabrics and other cosmetic trim to battery box NICE TO HAVE

TBD

NOT STARTED

Seats

Seats Mock-up (optional)
• Fabricate and install flat panels in wood to verify seating position, harness pass-thru, visibility, steering wheel and pedal position
• May need to mock-up seatback using flat sheets

1 week

DONE

Manufacture Seats Flat Panels
• Machine Molds
• Fabricate all seats flat panels in carbon fibre (can include ballast box too if also flat panels)
• Bond flat panels to bottom panel/structural elements

2 weeks

NOT STARTED

Manufacture Seatbacks
• Fabricate tooling for non-flat panels
• Fabricate non-flat seatback panels
• Install seatbacks into car

2 weeks

NOT STARTED

Finishing Touches
• Fabricate foam padding and cushions and install
• Fabricate and install remaining fabric coverings
• Fabricate and install headrest
• Ballast box finishing touches (lid, tie-downs)
• Install harnesses

TBD

NOT STARTED

IN

Contingency Planning

  • If lockdown happens, manufacturing will be impacted as long as lockdown remains

Design Projects (Trim + Dashboard)

Task

Time Allocation

Status

Finalize Research + Concepting

2 weeks

IN PROGRESS

CAD design

4 weeks

IN PROGRESS

Materials Selection

2 weeks

IN PROGRESS

Supplier Interfacing

Assembly Plan

TBD

NOT STARTED

Core Team

Name (Term)

Responsibilities

On-site Capacity

Renzo (Co-op)

• Leading manufacturing of catamaran cover
• Form factoring of dashboard

On-site

Kristen (Co-op)

• Assisting with manufacturing
• Leading design for displays
• Infotainment liasing w/ Firmware

On-site

Sheila (School)

• Leading manufacturing of seats

On-site

Cordelia (School)

• PM for dashboard
• PM for seats

Remote

Lovisa (Co-op)

• PM of trim

Remote

Joy (School)

• Assisting with manufacturing
• Form factoring of doors
(door handle)

On-Site (question)
Dependent on COVID situation

Geoffrey (Co-op)

• Form factoring of trim
• Form factoring of doors
• Assembly plan for doors

Remote

Onboarding Project

Onboarding Project Instructions

  • No labels