Aux Battery
Tested 25-ish cells (approx 60 total)
CAD - need mount (will be late by few)
Cells may need balancing, will add balancing taps
Deliverable: Finish the CAD for the 24th
Enclosure
Design overall → opening mechanism not optimal
Will recad with bare min.
Box will rest on the floor of aero
Shem → working on removal tool
Manufacturing enclosure will have to wait
top, bottom, holder will print (module)
Ports have been found, need to confirm
Wire gauge - ? 2-6 AWG?
It was determined the module holders will be epoxied to the base of the enclosure
Deliverable: Tuesday get a new timeline for the enclosure + Design review
Board Mounts
Integration meeting happened, got lots of info for mounts
AFE almost done, carrier and current sense not
Ideal for current sense and carrier to be on top of each other
Saturday → sprint for mounts
Redesign, two brackets instead of two brackets and top plate
AFE and carrier the same size
Improve space for wiring, add standoffs for the mount
PVDR
Module Testing????
Manufacturing state → as soon as possible
Kostubh will draft a testing procedure for the pack to validate
Will be there Monday to discuss
Coulomb Counting
Telemetry moved to low-priority task
Looking into different integration methods for calculating SoC on STM32, should have some research by the next integrations meeting on Tuesday
currently doing research on viable algorithms and will be checking in with integrations on tuesday on our next steps based on the research
This week:
Apply for passes (HTN): shem, nicole, maggie, vaihbav
Nicole → rch session for first years