Assembly Name | Quantity | Dependency |
---|---|---|
Soldered Voltage Taps | 14 24 Double ones (11 Thick, 3 13 thin) 40 60 Singles (36 56 thin, 4 thick) |
|
Potted Busbar to Top Cell Holder | 1114 |
|
Soldered SigmaClad Busbars | 713 |
|
Modules w/ Cells | 110 |
|
Spot Welded Modules 1 | 5 with parallel connections done |
|
Total Modules | 1 |
...
Potting the top cell holders and soldering the voltage tap to busbars should be done throughout the weeks between working sessions whenever possible.
Current number of potted busbars (as of Nov. 8th): 11
Current number of soldered busbars (as of Nov. 8th): 7
Current number of soldered voltage tap sets (as of Nov. 6th): 0 - need to check in bay
The updated cell voltage tracker can be seen here: https://docs.google.com/spreadsheets/d/1C3MhkND7lfTybrjJ4YvUgX5Ml7Qa0hKz4aU-mdojsUQ/edit?usp=sharing
...
Placing the cells in the necessary order (steps 6-8) should be done throughout the week between working sessions depending on if we have the necessary materials (enough cells measured, and enough top and bottom plates) Current number of modules with cells (as of Nov. 6th) : 0
The updated cell voltage tracker can be seen here: https://docs.google.com/spreadsheets/d/1C3MhkND7lfTybrjJ4YvUgX5Ml7Qa0hKz4aU-mdojsUQ/edit?usp=sharing
...
Spot welding of the cells in the modules should take place whenever possible throughout the week.
Current number of spot-welded modules (as of Nov. 6th): 0
Current number of potted modules (as of Nov. 6th): 0
Expand | ||
---|---|---|
| ||
|
The rest of this timeline will offer ~14 days for conditional forecasting and any needed adjustments/ delays to the timeline. Which I am expecting to happen.