  • The steps referred to in this doc are found here: Module Step-by-Step Procedure

  • This page will have all relevant updates to where we currently are in terms of quantity of modules after it has been run through Donna

    • Please send updates of progress if working on modules throughout the week on the Mech-Battery-Box channel on Slack

Assembly Name

Quantity

Dependency

Soldered Voltage Taps

14 24 Double ones (11 Thick, 3 13 thin)

40 60 Singles (36 56 thin, 4 thick)

  • Nickel Strips

  • 28 AWG wire

Potted Busbar to Top Cell Holder

7 14

  • Busbars

  • Top cell holders (completed manufacturing)

Soldered SigmaClad Busbars

113

  • SigmaClad busbars cut

  • 28 AWG wire

Modules w/ Cells

110

  • Sets of cells measured

  • All assemblies above

Spot Welded Modules 1

5 with parallel connections done

  • All assemblies above

Total Modules

1

...

Potting the top cell holders and soldering the voltage tap to busbars should be done throughout the weeks between working sessions whenever possible.

Current number of potted busbars (as of Nov. 6th): 4

Current number of soldered busbars (as of Nov. 6th): 0

Current number of soldered voltage tap sets (as of Nov. 6th): 0 - need to check in bay

The updated cell voltage tracker can be seen here: https://docs.google.com/spreadsheets/d/1C3MhkND7lfTybrjJ4YvUgX5Ml7Qa0hKz4aU-mdojsUQ/edit?usp=sharing

...

Placing the cells in the necessary order (steps 6-8) should be done throughout the week between working sessions depending on if we have the necessary materials (enough cells measured, and enough top and bottom plates)

Current number of modules with cells (as of Nov. 6th): 0

The updated cell voltage tracker can be seen here: https://docs.google.com/spreadsheets/d/1C3MhkND7lfTybrjJ4YvUgX5Ml7Qa0hKz4aU-mdojsUQ/edit?usp=sharing

...

Spot welding of the cells in the modules should take place whenever possible throughout the week.

Current number of spot-welded modules (as of Nov. 6th): 0

Current number of potted modules (as of Nov. 6th): 0

Expand
titleSat. Nov 18, 2023
  • Spot welding the modules continued

  • Pick up from previous working sessions if need be

  • Continue potting modules

  • The rest of this timeline will offer ~14 days for conditional forecasting and any needed adjustments/ delays to the timeline. Which I am expecting to happen.