Weekly Updates

  • Asher - 2 mounts for the ventilation 
  • Henry - took rear hub nut measurements, looked into materials for hub nut tool, designed rear hub nut tool
  • Shi Jing - measurements for EV port extension taken
  • Yzabelle - unable to mark the critical fasteners, will do this weekend if someone is available to supervise
  • Jason - sick
  • Saad/Kimberly - investigated doors and made solidworks of a piece to attach door buckets at one end (M6?)

Action Items

...

Eric Fu

...

Michael Shiozaki

...

  •  order filament,
  •  find EV port 

Asher Lai/Henry

...

Wu

  •  mount right side vent, cut hole left side 
  • Jason He -  Recut the hole on drivers side for vent

Jason He

  •  Weight analysis (determine how much weight needed to make car 50/50) Yzabelle -

Yzabelle Go

  •  fasteners painted this week?
  •  Weight analysis (determine how much weight needed to make car 50/50)

Henry Wu

  •  Henry - begin to mill front hub nut tool 

Shi Jing/Henry

...

Wu

  •  Look at EV port
  •  Complete CAD of EV port extension, look at EV port Saad

Saad Shan/Kimberly

...

Liu

  •  make curved piece in solidworks, be ready to print for saturday.
  •  Get confirmation regarding both parts

...