Date
Attendees
Goals
- Determine the method of connecting cells together
- Determine the manufacturing techniques - including suppliers
- Determine a timeline to manufacture the modules
- Discuss a time to meet with mech to discuss a mechanical support - Contact: Adam Marchand
Discussion items
Time | Item | Who | Notes |
---|---|---|---|
5min | Sunstone Call |
| |
10min | Compression Pack Update |
| |
30min | Spot Welded Module Update |
| |
10min | Testing Methodology |
|
Action items
- Taiping LiGet a spot welder
- Minghao Ji Source nickel strips and tinned copper
- Manufacture prototype module before midterms.
- Tak Alguire Schedule meeting with Mech to discuss mechanical questions and battery box design
- Goal is to test the prototype module before Hell week
...