  • Hardware
    • AFE board should be done by June 9th for fabrication
    • Carrier board should be done end of June
  • Software
    • Basic functions should be implemented to protect the test modules by the end of June/early July

...

Driver Controls (Fidel Musa (Deactivated)Norman Chong (Unlicensed))

  • Hardware
    • Schematic All schematics should be done by end of June (button board + carrier board)
    • Carrier board PCB should be done by end of term, earlier if possibleJune
  • Software
    • Demo in June
    • Code should be complete by the end of the term, earlier if possibleJune/early July (by boards come in)

SWD Adapter (Norman Chong (Unlicensed))

...

  • Done by end of Fall 2017

Aux BMS (TBDTimea Ratiu (Unlicensed))

  • Schematic Block diagram should be done by the end of June
  • PCB done by end of term

Motor Interface Board (Fidel Musa (TBDDeactivated))

  • Decision as to how we're implementing this should be made by the end of JuneHardware
    • Looking into using STM32F0 as co-processor on carrier board
    • Board done by end of year
    • Prototype with two controller boards
  • Software
    • Proof of concept by end of term

Lights (TBD)

  • Hardware 
    • Lights should be chosen for the lights by end of June
  • Software 
    • Software should be done by the end of the term

Telemetry (Calder KitagawaKarl Ding)

...

Solar Interface (Titus Chow

  • We should settle on a solution by the end of JuneHardware
    • Probably using I2C slave boards


Orders

Elecrow

  • Board order on June 9th for AFE, Power Distribution, SWD Adapter, Controller Board rev4
  • Board order July 7 for BMS carrier, Driver Controls (carrier board only, no button board) 

Digi-key

  • One order on May 29
  • One order once Elecrow ships the boards out

...