2024/03/23
Announcements
ASC road fee
getting processed monday…
...
Did the layup to end gap between tub and roof
Back panel layup
Canopy cutout, needs to be sanded and cleaned
Stencils printed for headlights
This week: headlights, sidelights, back panels connection layup
Bodywork
E3 needs help
we will work on cuts and body work synchronously
Bat:
Battery box panels are all epoxied, had some gasket sealing issues that we decided to fix with tacky tape
Mido re-ran the sims for the cross-bars on ANSYS and they passed (Michael and Adan were also in the call)
Things left to do:
Full pack testing (Owen & Vaibhav)
Validating 3D-printed parts and attaching/installing them to the box (Nicole & Shem)
Some small miscellaneous things like drilling holes into M10 screws for cotter pins & whatnot…
...
FSU: Control arms welding this week, machined hubs and clevises so assembly can start this week
RSU: Carsium parts were given to E3 last week
BRK: Rotor material arrived, E3 set to machine caliper mounts, starting pedal manufacturing
STR: Jens completed design updates, waiting on VDR approval… if close to finals i will need to enact HUMMUS
Int:
steering wheel, canopy tilt, lanyard mounts sent for water jetting, to happen sometime next week
Roof tilt water jet parts to be added to same DXF before water jetting
interior panels final design review to happen next week
Steering coupling to be machined next week
Seat padding covers being selected by Jason
Horn mount design review pending
Chassis rewelds are set for this week, still swamped with FYDP
Elec:
Hardware - Continuing to support FW for mockup
...
Summary of SDC Leads Meeting
Commercial Van Training Course
email will be sent out later to schedule
classroom sessions next few months, road sessions in April
Giving Tuesday
$28,000 to be split amongst all design teams
need to write up proposal and SDC will distribute to teams based on need
Sandra Fleming Travel Fund
online application available (due in April)
up to $1000* - maybe more since historically they were low on applicants
Router in workbay
Engineering Computing doesn’t like our midsun wifi 😞
PVDR
elec - green
mech - red
VDR
mech - unreviewed
elec + battery - green
Track Fee
Yanshen Zhou confirm with IEF that they received payment
FILL OUT ASC FORM! Will close tmr
Sub-team Check-ins:
Aero
Ribs connection to tub this weekend
windshields coming back monday
E3 body work
they’re really busy…
meeting with Brian monday
headlights
to meet w forest
idea to minimize headlight area
floor panels getting cnc’d this week
...
SDC leads meeting next week
trailer certification
Sandra Fleming travel grant
FILL OUT FORM FOR COMPETITION!
VDR
Elec deadline today!
battery done
solar done
elec in progress
Mech deadline past wednesday
everything done, formatting in progress
PVDR resubmission
couple of comments - dynamics and chassis
...
Mech PVDR Re-submission - FINISH THIS WEEKEND!
chassis - done
dynamics - jonathan pushing
...
LEARN recruitment messages
midsun alumni spotlight - serial
ASC competition logistics working sessions - Saturday @ 2:00 PM
W24 WEEF applications opened
plan to apply to race equipment
claim rest of Dean’s funding once vehicle is complete
2024/01/06
VDR DUE January 31!
PVDR resubmission needs to be done!!!!
battery box W24 timeline
mainly testing
Jenna Kong has timeline
not super extensive
battery enclosure at demtool for powder-coating
owen, shem, nicole, vaibhav, etc.
interiors
roof-latching + tilting
canopy tilting
miscellaneous small tasks
seats…ballast box
Divit designing seat mold
3 including adan
rear camera mount
need to manufacture
pedal mounting
dynamics
DEADLINE: powder-coating sendout - beginning of March
matt has excel timeline
designated mech co-op
after sendout = assembly
april: tuning
matt, couple first years, jonathan
aero
CNC mold list to send to Graeme
mold layup schedule based on Graeme schedule
clean out sanding room by this Tuesday!
windshield mold done
thermoformed tuesday
headlight cutouts made next week
prioritizing flat panels
michael to make wheel wells
matt, jasmine, vu?
...
Meeting w/ Peter + graeme
Thursday, November 9th
leads critical to vehicle completion REQUIRED!
mech leads
mitch (fw)
forest
jonathan
+ tech leads for next term
to discuss feasibility of vehicle completion
pre-meeting check in Wednesday?
7 PM
PVDR Deadline Monday!
Potluck Friday!
HUMUS
Sub-team Progress Check
...
Meeting w/ Peter + graeme
Thursday, November 9th
leads critical to vehicle completion REQUIRED!
mech leads
mitch (fw)
forest
jonathan
+ tech leads for next term
to discuss feasibility of vehicle completion
pre-meeting check in Wednesday?
7 PM
PVDR Deadline Monday!
Sub-team Progress Check
Mech Gen
...
ASC 2024 Pre-Event Team Status
WEEF Applications due October 31st
Sub-team Progress Check
Mech Gen
...
get F23 EngSoc wishlist by END OF TODAY
F23 second-half milestones + initiatives
i.e. manufacturing goals, resume reviews, etc.
...
~25 people out to 101
HW validation with PD
FW members waiting for tasks
need more HW people to get boards done
AFEs as well?
Priority
solar testing
MCI
BMS boards
...
September 2023 | ||||||
---|---|---|---|---|---|---|
Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
3 | 4 | 5 | 6 SDC Design Team Showcase 3 - 5 PM
| 7 First General
| 8 | 9 Sub-team 101s |
10 | 11 Competition Overview (All teams) | 12 | 13 | 14 | 15 Hack the North (RESTRICTED BAY ACCESS) | 16 Hack the North (RESTRICTED BAY ACCESS) |
SDC Design Team Showcase Signup
...