title13 December 2023 - W2023 Plans, Elec Integration, and Enclosure Assembly

Meeting Notes for December 13, 2023 MeetingMeeting Topics
Things we to talk about Wednesday:

  • Elec Integration plan for battery next term

  • What has to be done?

  • Who will be involved?

  • When will we be able to get it done?

  • Assembly plan

  • General overview

  • New check-in & project tracking structure

  • Trello & Confluence

  • Individual project updates

  • Avoiding past mistakes

Meeting Notes:Elec Integration plan for battery W2024:What has to be done?

  • Competition in July, we dont know where Owen’s gonna be

  • Battery pack with everything assembled by end of next term

  • Figure out where all electrical components are going to be placed (confirm positioning with Hardware)

  • Figure out wire lengths

  • LV can be over-speced, HV can’t because insulation is so thick (can’t bend easily)

  • Need custom busbars for main battery pack

  • ex. end busbar for pack terminals need to be bent backwards, L shaped

  • need to build up all the busbars

  • Rear busbars can be built now, others can’t because positioning not confirmed.

  • Need plates to place PCBs & solar relay & everything else

  • Make sure all the modules fit properly, might need changes if things go wrong. Including baffles, fans and all.

  • Terminals and solar relays are the same (from MSXII)

Who will be involved for elec integration?

  • Hardware: Jonathon, Forest

  • Battery: After enclosure is finished do modules, manufacturing spare modules, electrical integration.

  • Doesn’t hurt to talk to other teams in the SDC. Sit-down meeting with questions prepared would be useful.

Endgoal of W2024 for elec integration

  • Full pack complete with all boards & components connected

  • Assuming BMS is complete, check Hardware’s timeline

Module Testing Side Tangent

  • One has been tested, Forest says its good

  • Placed a thermistor in the middle of module: 10C change (20-30mins run time @ 10Amps)

  • Testing plan is there, work with Forest on it next term

  • Goal is to make all modules, then test W2024

  • Modules with weak busbar potting. Tried reapplying potting onto top cell plate, didn’t turn out well. Didn’t seem to stick.

  • Is potting necessary? Just to hold sigmaclad in place. Tight spacing between modules, moving around w/ vehicle moving, good to have potting. Potting will be done after testing.

  • Potting cells after testing (potting material poured over welded connections), potting busbars is necessary. We have to figure out how to redo, if top cell plates can’t be reused, might have to rip them out for new ones.

  • Potting process is fine, procedure just weren’t followed correctly.

  • Owen says we should do internal resistance test on all finished modules (won’t take long, just multimeter to read resistance)

  • Will do both individual module test and full pack test for thermals w/ BMS hooked.

Enclosure Assembly Plan

  • Nicole has a plan (rough outline)

  • Goal is to print baffles and everything using leftover ABS

  • Nicole will print

  • Owen’s friend can print some things

  • Nicole will put together a sheet of who’s printing what

  • Vaibhav will update the Enclosure BOM, put everything small and ez to lose in Enclosure Plastic Bag

  • Hydrophobic mesh is pricy ($30), hose clamp ($4). Push things we don't need immediately for next term to buy with WEEF/ENGSOC money.

  • Finish assembly before start of W2024

  • Need to 3d print validation device to ensure boards sit where they’re supposed to sit. Will look like modified version of the baffles. Design in the works. Nicole is working on it.

  • Validation for feet onto chassis

New check-in & project tracking structure

  • Bring back trello, with projects updated by only core members (and roping new members in if the consistently are coming in).

  • Updates should be made as soon as something is done, not just during check-ins.

  • Fall term check-ins (Jericho’s perspective)

  • Not so bad, because of going directly to ppl working on projects

  • Confluence gets convoluted & outdated, Trello is more readable

  • Clearer structure of parameters would’ve been helpful. What materials to use, how many parts to use. Stricter idea of what it should’ve been.

  • Trello:

  • Active updating, journal entry updates

  • Confluence:

  • Wiki, ctrl c + ctrl v stuff on trello

  • Project specific meetings:

  • Have specific meetings for each project (elec integration w/ Hardware & module manufacturing)

  • Make sure ppl online aren’t in the dark

  • Check-Ins

  • General overview of what’s going on in the subteam

  • Owen runs

  • Have something similar to Summer, not just done after work term. We won’t have as much time to dedicate to onboarding. Check-ins were good way to know whats going on and what projects are available. If it’s right after working session, ppl just left cus they were tired after the work session.

  • Check-ins ideally done day after a working session

Meeting times:

Winter Onboarding Side Tangent:

  • Maybe 5-10 new members peak in the beginning

  • Not spend a lot of time on it

  • If not a lot of ppl leads/lead in training can assign project to new member

  • No module spec’ing or make your own module

Expand
titleJan 3, 2023 Module Manufacturing

Pre-Meeting Notes:

  • What is the current state of modules?

    • 9 modules manufactured

    • 1 aux battery manufactured?

  • What do we need to do W24?

    • 9 modules + 4 spare modules manufactured and validated

    • 3 aux batteries

  • Review Module Testing Plan with Micah

  • Review Modules with Micah

    • Does he have any concerns with any choices we made?