Tub

Male plug design - February 27th

Foam split up in MasterCAM - March 18th

Start mold manufacturing - March 20th

Conceptual Resin Lines Concepts - March 31st

Reach out to professions for consult - March 31st

Build structure for left plug - April 1st

Finish left of half plug - April 3rd

Build structure for right plug - April 15th

Finish right half of plug - April 17th

Material cut plan for fiberglass - June 23rd

Finish surface prep - June 30th

Material Prep - June 30th

Fiberglass layup - July 1st

Build mold platform - July 2nd

Material cut plan for carbon - July 6th

Material prep - July 7th

Carbon fiber Layup - July 8th

Michael

Entire team to help with mold prep and construction

Wheel Cover

Conceptual design of mechanism - March 16th

DFM/DFA review with Michael - March 23rd

Mold CAD concept - March 30th

Finalize mold CAD - April 6th

Wheel cover CAD in the car - April 30th

Matthew

Tania

Dhruv

Sonny

Janushan

Jeniton

Aditi

Melinda

Ribs

Conceptual rib design - December 30th

CAD of ribs - February 1st

Rib alignment conceptualization - February 17th

Rib alignment review with Michael - February 24th

Ribs FEA with roof - April 12th

Finalize rib design - April 30th

Rib layup - May 20th

Matthew

Nathan

Michael , Jens, Mido (for FEA review)

Wheel Well

TBD - Dependent on Dynamics

Jasmine

Floor Panel

Concept design of floor (integration) - March 21st

Floor CAD complete - March 31st

Floor FEA - April 11th

Foam breakdown of floor - April 15th

Layup - May 6th

Michael

Roof

Mold concept - March 21st

Mold with cutout and alignments - March 31st

Foam breakdown of mold - April 10th

Start Machining - July 26th

Finish mold surface prep - September 15th

Material prep - September 15th

Layup - September 16th

Canopy

Mold concept - March 21st

Mold with cutout and alignments - March 31st

Foam breakdown of mold - April 10th

Start Machining - July 3rd

Material cut plan for fiberglass - July 23rd

Finish mold surface prep - July 31st

Fiberglass material prep - July 31st

Material cut plan for carbon - August 3rd

Material prep - August 4thth

Carbon material prep - August 5th

Layup - August 5th

Aero-Chassis Integration

Finalized concept - April 30th

Michael

Matthew

Mido

Ventilation

Ventilation concept - August 31st

Michael

Lights

Refer to this confluence page:

https://uwmidsun.atlassian.net/l/cp/X1cGk1Xm

Jasmine

Fatima

Ryan

Dhruv

Althea

Carina

Noah

Edward

Jeniton

Windshield

Windshield Design - March 1st

Windshield Mold CAD Concept - March 12th

Back Windshield Design - March 12th

Back Windshield Mold CAD Concept - March 12th

Finalized Mold CAD - Dependent on Thermoformer

Plan to have Windshield in the bay by - August 15th

Integration into Canopy - TBD