Project | S2021 Term | F2021 Term |
Adhesive Curing Fixture | Fully Complete Machine during July |
|
Bend Fixture | Fully Complete Machine during July |
|
Composite Failure Theory | Fully Complete |
|
General Composite Testing | Fully Complete End of S2021 |
|
General Adhesive Testing | Fully Complete End of S2021 |
|
Seats Testing | All Remote Aspects End of S2021 | In-Person Testing Fully Complete |
Aero-Chassis Testing | All Remote Aspects End of S2021 | In-Person Testing Fully Complete |
Design of Experiment | Fully Complete End of S2021 |
|
General Material Testing Project Stages
Project Stages |
Test Plans |
Inventory + Supplier Interfacing |
Test Setup Preparation (Test Specimen, Test Apparatus, etc.) |
Onsite Testing |
Simulation of Tests |
Test Report |
...