  • Figure out how people can maximize the amount of on-site work (take things home, go into bay, what they can accomplish)

  • Figure out all tasks that can be delegated + how can we make them so that those people can help the onsite team (creating BOMs, Digikey, test plans)

  • Role shifts / assignments --> onsite vs. offsite leads (onboarding), who needs support where people take stuff done but end up blocked or can’t --> how to minimize that, how to achieve the mental state to push or ask for support --> will people be more motivated if given more responsibilities?

Term Goals

Note

No specific dates since COVID might just screw everything up… will use time estimates 😢

Details

Priority

Timeline

Assembling final versions of boards

  • PD, Lights, Steering, Solar, UV Cutoff, BMS Carrier

Status
colourRed
titleHigh

4 months

Final designs for boards (for sendoff by EOT)

  • Pedal, Precharge, UV Cuttoff?, Solar?

Complete all board mounts

Status
colourRed
titleHigh

4 months

Complete wiring diagram

  • Make the importance of the tasks more clear (smile)

  • Aren’t too far from completion

Status
colourRed
titleHIGH

End of June

MANDATORY WORK SESSIONS 😤

Finalize enclosure layouts

  • Feedback for interiors

Status
colourYellow
titleMedium

dependent on Interiors

Validation / Testing

  • Powertrain, MCI

  • Charger Interface

    • Elcon Charger to mockup battery

  • Precharge

  • BMS

    • Connect power supply to each channel, verify lower and upper faults

  • Solar Sense → can test outside (tongue) (MPPT layout)

  • Don’t have a load to test motors… Need to put it on the car

Status
colourYellow
titleMEDIUM

Further testing motors depends on mech (need rolling chassis)

BMS → dependent on battery, also need BMS Carrier assembled

HV integration into mockup

Status
colourGreen
titleLow

Complete all harnesses

Finalize enclosure layouts

Complete all enclosures

Assemble all items

...

Telemetry, Headlights and Cameras (w/ Interiors)

Status
colourGreen
titleLow

Sorry, Renzo

Carryover from Fall 2020

Carryover from Winter 2021

All onsite tasks:

  • Assembling final versions of boards (HW)

    • PD

    • PS (done)

    • Steering

    • Lights

    • Solar

    • UV Cutoff

    • Centre Console (done)

    • Current Sense (done)

  • Motor Sense Validation (HW)

    • At the stage of integrating Sense to Controllers

    • Blocks all of Power Train

  • High voltage testing (HW)

    • Integration Testing

    • Blocked by Motor Sense Validation

    • Blocked by Pre-Charge integration testing

  • Assemble final versions of most boards (excl. AFE, DCDC, Charger interface, MCI) (January)

    • HW validation for new versions

    • Notes:

      • Aashmika has the reflow at home to assemble most boards

      • if lockdown happens, this can still be done at Aashmika’s house.

    • Unit test boards once they return

      • if designs are flawed, board needs to be resent (at any stage)

  • Integrate into mockup (February) - must be onsite

    • Displays

    • Horn

    • Cameras

    • Telemetry Router

  • Mockup Testing

    • Solar

    • BMS Full (Pending Battery pack, and other testing)

    • MCI, Limit testing for Motors (includes carryover from F2020)

    • Full Mockup Integration (w/ displays)

    • Worst case: bleed into Spring

  • Complete all harnessing/make diagram for full vehicle (near EOT)

    • Includes layout

    • Note: this is offsite, if lockdown, will move this task to Jan

  • Finalize Enclosures Layout
    (to plan for post W2021)

Spring Term

  • Assembling Final Versions of Boards

  • Complete all board mounts

  • Complete all harnesses

  • Complete all enclosures

  • Assemble all items

...

Name (Term)

Responsibilities

On-Site Capacity

Aashmika (School)

• Assembly of final versions of boards
Integration into mockupPrecharge

ASC VDROnsite
Remote (Toronto)
Available on most weekends
• Can possibly take some boards home to work on, during the week

Micah
(School)

• Motor sense validation
HV testing for mockup
• Enclosures + enclosure layoutsEnclosures finalization

• On Sitesite, focus on battery box (1 month)
• Part-time + 3A… 😅

James L
(Co-op)

• Assembly of final versions of boards
• Telemetry Diagram

• Remote, On Site in February?
• Can do hand soldering, will need equipmentwill in in-person in Fall 2021
• Most likely can’t help

Nita
(School)

OnboardingAssemble PD (reflowed on side, hand-assembled the other side)
Acquiring Samples
Task force for diagram making

• Remote
• Can maybe visit on some weekends, cannot take home equipment (moving)weekends but will be overloading during the term

Liam
(School)• Onboarding
• BOM Consolidation
• ASC BMS VDR

• Assembly of final versions of boards

• Remote
• Probably won’t be in Waterloo, also does not have equipment• has equipment to do assembly / validation without being in loo

Kristen
(School)

• Harnesses?

• On Site
• Grunt work (smile) that requires limited hardware knowledge

Ricky
(SchoolCo-op)

Onsite TrainingOnboarding?

• Onsite• Onboarding 😃

Returning Members

  • Other On SIte Remote Members: Ricky Huang, Janvi, Ricky L, Alastair

  • On-Site Members: Odianosen, Vinai, Wyatt, Hunter

Onboarding

...

Assembly - Aashmika

...

Reflow - James

...

How to use equipment (testing, soldering, etc.) - Liam

...

Troubleshooting - Nita

...

Harnessing

  1. Pool resources in a deck + go through video,

...

Testing Firmware (using babydriver, etc.)

Tour of entire bay → ping core channel (organize a video → Kristen)

...

PresentationKnowledge Share

PresenterLead

Date

AssemblyWeek 1

Aashmika

24 Apr

ReflowWeek 2

James

How to use equipment (testing, soldering, etc.)

Liam

Troubleshooting

Nita

Testing Firmware

Harnessing

...

Hardware board design process onboarding still available

Current onboarding content covers board design but we should create resources for on-site work (videos = recordings on Zoom + PPTs)

Nita

Week 3

James

Week 4

Ricky

  • Goal for this term

    • a dummy’s intro to the electrical sub-systems 2.0

  • Previous onboarding

    • a dummy’s intro to the electrical sub-systems

    • design a board

    • how to be useful onsite

  • Engagement ideas (after members watch videos)

    • Jump on a call to do worksheets together

    • Kahoot

Purchases

Item(s)

Estimate Price

Source

board sendout (midterm)

Status
titleWEEF W2021

infotainment screen

Status
titleEngsoc w21

Maha Batteries (Battery Box?)

Status
colourBlue
titleWEEF F2020

Label maker

Status
colourBlue
titleWEEF F2020

Pick and Place ($11k) → Neoden?

  • $3000 for certifications (apply for more funding)

  • + tax + import fees + USD + shipping 😞

  • SSDC doesn’t like aliexpress 😞

Status
titleWEEF W2021

Tasks for Off-site Members

Task

NameDifficulty

DescriptionNotesDifficulty

Power Consumption Evaluation

Status
colourRedYellow
titleDifficultModerate

Wiring Diagram

Status
colourYellow
titleModerate

Component Investigations

Status
colourGreen
titleEasy / Manageable

  • Mockup Diagram task force

  • Onboarding material?

    • For returning members: Component investigations + specs (what they do, what they provide in a circuit, how to find one that fits project requirements) - to help new members, and help documentation

  • Investigations

    • A365 packaging tool

  • Library Management

    • Figure out how to get rid of duplicates and know which components get updated

  • Research tasks…

    • Not priority for new members since we are on critical path

...

  • Reviews for all tasks together (smile)

    • Last Saturday of each month? Extended standup 😞

  • Buddy system (2-3 members w/ a lead)

    • Leads combine tasks to have groups work on them together (Kristen (smile))

    • Saturday work sessions

    • Standups once a week → Wednesdays

Expectations for Next Term

  • RETAIN MEMBERS 😃

  • Join On-Site weekly standups to get a better grasp of overall elec progress, improve knowledge

...