Project | Goal | OG Date | Date (March) | Priority | ||||||
---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover | Complete manufacturing | 2 months | 3 months End of AprilMay |
| ||||||
Seats | Complete manufacturing
| 2 months | 2 Months End of July |
| ||||||
Doors | Complete FULL manufacturing plan (EOT W21)
** Any Structures changes to hinges need to be communicated | 2 months | 2 MonthsManufacturing Time: 2 months Commitment for Manufacturing Completion: Mid-F21 |
| ||||||
Trim | Complete detailed design
| 4 months
Trim Integration: 2 months |
| |||||||
Dashboard | Complete detailed design | 4 months Manufacturing: 3 months Integration: 1-2 months |
| |||||||
Displays | Ensure Infotainment display works Ensure Infotainment display works FW) Note: 2 screens is mounted with dashboard and HW integration | 2 months | 4 months Driver Display Design Commitment: End of April Hi-Fi Wire Commitment: End of S21 Test Screen before going into the car (pre-Dashboard integration) |
“easiest” |
...
Project | Task | Time Allocation | Status | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT |
All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT | ||||||||
Catamaran Cover | Manufacture Molds
| 2 weeks |
| ||||||||
Manufacture Major Battery Box Panels (bottom + side walls + lid)
| 3 weeks |
| |||||||||
Manufacture Internal Parts | 1 week |
| |||||||||
Material Testing
| 1 week |
| |||||||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week |
| |||||||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks |
| |||||||||
External Finish
| TBD |
| |||||||||
Seats | Seats Mock-up (optional) | 1 week |
| ||||||||
Manufacture Seats Flat Panels | 2 weeks + 1 week = 3 weeks |
| |||||||||
Manufacture Seatbacks | 2 weeks + 1 week = 3 weeks |
| |||||||||
Finishing Touches | TBD |
|
...
|
Integration with Subteams/Dependencies
Catamaran depends on:
Aero-chassis BP integration
Battery box modules ready
Dynamics assembly
Seats depends on:
Bottom panel + chassis integration
Floor panels need to be added into the vehicle
Welding items for chassis
B,C-bulkheads Integrated
Dashboard depends on:
Dynamics
Aero-Chassis Integration (A-bulkhead, A-Plane)
Interior doors
Electrical & Battery Box need to be integrated so we can route wires
Depends on Displays & cameras to be ready
Contingency Planning
If lockdown happens, manufacturing will be impacted as long as lockdown remains
...