Battery Box Workflow

Project Deadline

Project

Fall 2023 Sub-Tasks

Deadline

Assignee

Notes

Aux Battery

Finish CAD - Sept 24
Prototype Module - Oct 1
Aux Design Freeze - Oct 17
One module fully tested and complete - Oct 20
Aux Enclosure Manufactured - Oct 31
All manufactured - Nov 15

November 30, 2023

Darton + Jenna

Status: Design

Battery

Manufacturing process draft - oct 7

List of hardware - oct 7

Terminal Covers - TBA

All modules manufactured - Nov 30

November 30, 2023

Donna

Status: Design + Manufacturing

BMS

Colomb counting

N/A

HW + FW
Eric + Kostubh

SoC Estimation

Board Mounts

Finish CAD - Sept 16
Design freeze - Sept 22
Prototype - Sept 22
Manufacturing - Sept 30

September 30, 2023

Maggie + Vaibhav

Status:

Design - Done (27-09)

Testing

Enclosure

Enclosure Design- Sept 30

Prototyping check - October 15

Enclosure jig - October 7

Design + material - Sept 30

Enclosure Box - Nov 2nd
Fan Integration - Nov 15
Wire Harnessing - Nov 30

November 30, 2023

Shem + Nicole

Design - In progress

Manufactruing - starting

PVDR

Draft Completed → Sept 23

Integration + Timeline

September 30, 2023

Owen

Draft - done