This document outlines the tasks for the Interiors team for the Winter 2021 term.
Term Goals
Project | Goal | Date | Priority |
---|---|---|---|
Catamaran Cover | Complete manufacturing | 2 months | HIGH |
Seats | Complete manufacturing | 2 months | HIGH |
Doors | Complete manufacturing plan | 2 months | HIGH |
Trim | Complete detailed design | 4 months | MEDIUM |
Dashboard | Complete detailed design | 4 months | MEDIUM |
Displays | Ensure Infotainment display works | 2 months | LOW |
Manufacturing Projects
Project | Task | Time Allocation |
---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT |
Catamaran Cover | Install catamaran items on bottom panel + chassis | 2 weeks |
Manufacture Major Battery Box Panels (bottom + side walls of box) | 3 weeks | |
Manufacture Flat Panels | ||
Assembly of battery box panels | 2 weeks | |
Mount Latches | 1 week | |
Manufacturing Misc. (Components that go into the battery box) | TBD | |
Seats | Seats Mock-up (optional) | 1 week |
Manufacture Seats Flat Panels | 2 weeks | |
Manufacture Seatbacks | 2 weeks | |
Finishing Touches | TBD |
Design Projects (Trim + Dashboard)
Task | Time Allocation |
---|---|
Finalize Research + Concepting | 2 weeks |
CAD design | 4 weeks |
Materials Selection | 2 weeks |
Supplier Interfacing Assembly Plan | TBD |
Core Team
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (Co-op) | • Leading manufacturing of catamaran cover | On-site |
Kristen (Co-op) | • Assisting with manufacturing | On-site |
Sheila (School) | • Leading manufacturing of seats | On-site |
Cordelia (School) | • PM for dashboard | Remote |
Lovisa (School) | • PM of trim | Remote |
Joy (School) | • Assisting with manufacturing | On-Site |
Geoffrey (Co-op) | • Form factoring of trim | Remote |