Hardware
Design Projects
Project | Status | To-do |
---|---|---|
Pedal Board |
|
|
Steering Stalk |
|
|
Center Console |
|
|
Telemetry |
|
|
BMS AFE |
|
|
BMS Carrier |
|
|
BMS Current Sense |
|
|
Controller Board |
|
|
Validation & Integration Projects
Project | Status | To-Do |
---|---|---|
Motor Controller Interface |
|
|
Solar Sense |
|
|
Power Distribution |
|
|
Driver Display |
|
|
Pre-Charge |
|
|
EV Charger |
|
|
Retrospective
Track Days
- The car was not ready for testing on both track days
- The first track testing was cancelled due to a faulty resistor joint on the AFE
- The second track testing was cancelled due to a faulty relay in the battery box
- The team did not have sufficient knowledge and experience to debug the issues before the deadlines
- Took too long to find out the causes of the issues
- There wasn't a plan in place or enforced to make sure the car is 100% ready the night before the track day
Board Design
- The new driver control board design requires more prototyping iterations and time than expectation
- We should start to prototype the different designs much earlier in the term
- The new members need time to learn how to use Altium and familiarize with hardware team's workflow
Project Management
- Did not take advantage of the project management tools to make sure the projects on track
- The planned deadline is not being enforced
- Did not account for the prototyping time