Weekly Goals
Week | End of Week Goals |
---|
July 5 - 11 | Chassis: (All done!) Access to Welding Room Finish sanding & assembling jigs (done) Drop off parts for welding Assembly more jigs Welding components onto Chassis
Aero: (Bleeding into week of July 12 - due to booking conflicts with Waterloop) Battery Box: |
July 12 - 18 | Chassis: Aero: Finish prepping side panel molds Begin material prep for side panels layup Make a decision if we want to layup both - offline finish side panel molds 3, 4 b bulkheads sand, potentially make blank and machine second mold as well (based on SDC)
Composites: |
July 19 - 25 | |
July 26 - Aug 1 | |
| |
Instructions: Please fill this out BEFORE the onsite check-ins
Date | Individual | Goals for Today | Progress / Updates |
---|
| Micah Black | | Continued Battery Spot Welding |
July 8, 2021 | Mackenzie Lui, Kyle Lacson | Transport excess material to cold storage facility, set up paint guns. | Paint guns |
| | | |
| | | |
| | | |
| | | |
| | | |