This document outlines the tasks for the Interiors team for the Winter 2021 term.
Term Goals
Project | Goal | OG Date | Date (March) | Priority |
---|---|---|---|---|
Catamaran Cover | Complete manufacturing | 2 months | 3 months End of May | HIGH |
Seats | Complete manufacturing
| 2 months | 2 Months End of July | HIGH |
Doors | Complete FULL manufacturing plan (EOT W21)
** Any Structures changes to hinges need to be communicated | 2 months | Manufacturing Time: 2 months Commitment for Manufacturing Completion: Mid-F21 | HIGH |
Trim | Complete detailed design
| 4 months
Trim Integration: 2 months | MEDIUM | |
Dashboard | Complete detailed design | 4 months Manufacturing: 3 months Integration: 1-2 months | MEDIUM | |
Displays | Complete design of Driver Display Ensure Infotainment display works FW) Note: 2 screens is mounted with dashboard and HW integration | 2 months | 4 months Driver Display Design Commitment: End of April Hi-Fi Wire Commitment: End of S21 Test Screen before going into the car (pre-Dashboard integration) | LOW “easiest” |
Manufacturing Projects
Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. Strongly recommend we do this asap so that we don’t run into problems when it’s too late.
Project | Task | Time Allocation | Status |
---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT | IN PROGRESS All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT |
Catamaran Cover | Manufacture Molds
| 2 weeks | NOT STARTED |
Manufacture Major Battery Box Panels (bottom + side walls + lid)
| 3 weeks | NOT STARTED | |
Manufacture Internal Parts | 1 week | IN PROGRESS | |
Material Testing
| 1 week | NOT STARTED | |
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week | NOT STARTED
| |
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks | NOT STARTED | |
External Finish | TBD | NOT STARTED | |
Seats | Seats Mock-up (optional) | 1 week | DONE |
Manufacture Seats Flat Panels | 2 weeks + 1 week = 3 weeks | NOT STARTED | |
Manufacture Seatbacks | 2 weeks + 1 week = 3 weeks | NOT STARTED | |
Finishing Touches | TBD | NOT STARTED
|
Integration with Subteams/Dependencies
Catamaran depends on:
Aero-chassis BP integration
Battery box modules ready
Dynamics assembly
Seats depends on:
Bottom panel + chassis integration
Floor panels need to be added into the vehicle
Welding items for chassis
B,C-bulkheads Integrated
Dashboard depends on:
Dynamics
Aero-Chassis Integration (A-bulkhead, A-Plane)
Interior doors
Electrical & Battery Box need to be integrated so we can route wires
Depends on Displays & cameras to be ready
Contingency Planning
If lockdown happens, manufacturing will be impacted as long as lockdown remains
Design Projects (Trim + Dashboard)
Task | Time Allocation | Status |
---|---|---|
Finalize Research + Concepting | 2 weeks | IN PROGRESS |
CAD design | 4 weeks | IN PROGRESS |
Materials Selection | 2 weeks | IN PROGRESS |
Supplier Interfacing Assembly Plan | TBD | NOT STARTED |
Core Team
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (Co-op) | • Leading manufacturing of catamaran cover | On-site |
Kristen (Co-op) | • Assisting with manufacturing | On-site |
Sheila (School) | • Leading manufacturing of seats | On-site |
Cordelia (School) | • PM for dashboard | Remote |
Lovisa (Co-op) | • PM of trim | Remote |
Joy (School) | • Assisting with manufacturing | On-Site |
Geoffrey (Co-op) | • Form factoring of trim | Remote |