This document outlines the tasks for the Interiors team for the Winter 2021 term.
Term Goals
Project | Goal | OG Date | Date (March) | Priority |
---|---|---|---|---|
Catamaran Cover | Complete manufacturing | 2 months | 2 months End of April | HIGH |
Seats | Complete manufacturing
| 2 months | 2 Months | HIGH |
Doors | Complete manufacturing plan ** Any Structures changes to hinges need to be communicated | 2 months | 2 Months | HIGH |
Trim | Complete detailed design | 4 months | MEDIUM | |
Dashboard | Complete detailed design | 4 months | MEDIUM | |
Displays | Ensure Infotainment display works | 2 months | 4 months End of April | LOW “easiest” |
Manufacturing Projects
Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. Strongly recommend we do this asap so that we don’t run into problems when it’s too late.
Project | Task | Time Allocation | Status |
---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT | IN PROGRESS All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT |
Catamaran Cover | Install catamaran items on bottom panel + chassis | 2 weeks | NOT STARTED |
Manufacture Major Battery Box Panels (bottom + side walls + lid) | 3 weeks | NOT STARTED | |
Manufacture Internal Parts | NOT STARTED | ||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week | NOT STARTED | |
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks | NOT STARTED | |
External Finish | TBD | NOT STARTED | |
Seats | Seats Mock-up (optional) | 1 week | DONE |
Manufacture Seats Flat Panels | 2 weeks | NOT STARTED | |
Manufacture Seatbacks | 2 weeks | NOT STARTED | |
Finishing Touches | TBD | NOT STARTED |
Contingency Planning
If lockdown happens, manufacturing will be impacted as long as lockdown remains
Design Projects (Trim + Dashboard)
Task | Time Allocation | Status |
---|---|---|
Finalize Research + Concepting | 2 weeks | IN PROGRESS |
CAD design | 4 weeks | IN PROGRESS |
Materials Selection | 2 weeks | IN PROGRESS |
Supplier Interfacing Assembly Plan | TBD | NOT STARTED |
Core Team
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (Co-op) | • Leading manufacturing of catamaran cover | On-site |
Kristen (Co-op) | • Assisting with manufacturing | On-site |
Sheila (School) | • Leading manufacturing of seats | On-site |
Cordelia (School) | • PM for dashboard | Remote |
Lovisa (Co-op) | • PM of trim | Remote |
Joy (School) | • Assisting with manufacturing | On-Site |
Geoffrey (Co-op) | • Form factoring of trim | Remote |