Stage | To-Do List | Status | DRI | Due Date | |
---|---|---|---|---|---|
2 | Chassis Post-Welding Analysis | Blocked until we can be on campus. Need to measure and 3D model the chassis for simulation and interference checks | ASAP Serves as another validation step for the reinforcement solution method | ||
1 | Down select material choice for panel solution through research (CF sandwich panel, aluminum sheet metal, steel sheet metal) | Done | Done | ||
1 | Get updated masses for vehicle assembly | Done but could be improved S2021 Updated Masses of Sub-Team Assemblies - Mechanical - Confluence (atlassian.net) | 2021.06.05 | ||
1 | Vehicle Collision + Collision Object Setup Exploring running the bar into the chassis? Find force then push? | In Progress | 2021.06.05 | ||
1 | Mesh Convergence Studies on tube solutions simulations | In Progress - Blocked by remote desktop offlinecould be improved | Tommy Tran2021.06.05 | ||
2 | Structural Reinforcements Solution Simulations | In Progress - Blocked by remote desktop offline | Min Qian Lu (Deactivated)2021.06.05 | ||
1 | Research on Sheet Metal Design Space in terms of ASC Regs, Occupant Cell/Space requirements, Assembly Interference, and component design of Sheet metal mounting | In Progress | |||
1 | Updated Mass and Assembly | Done - But could be improved |