Carryover from Fall

Winter Tasks

All onsite tasks:

  • Motor Sense Validation (Hall-effect issues)

    • Pending Tritium or Iowa State University

  • High voltage testing for mockup (FW & HW)

    • Waiting for Motor Setup

  • Cell balancing + BMS Testing

    • Requires FW & HW

  • Assemble final versions of most boards (excl. AFE, DCDC, Charger interface, MCI) (January)

    • HW validation for new versions

    • Notes:

      • Aashmika has the reflow at home to assemble most boards

      • if lockdown happens, this can still be done at Aashmika’s house.

    • Unit test boards once they return

      • if designs are flawed, board needs to be resent (at any stage)

  • Integrate into mockup (February) - must be onsite

    • Displays

    • Horn

    • Cameras

    • Telemetry Router

  • Mockup Testing (February - April)

    • Solar

    • BMS Full (Pending Battery pack, and other testing)

    • MCI, Limit testing for Motors (includes carryover from F2020)

    • Full Mockup Integration (w/ displays)

    • Worst case: bleed into Spring

  • Complete all harnessing/make diagram for full vehicle (near EOT)

    • Includes layout

    • Note: this is offsite, if lockdown, will move this task to Jan

  • Enclosures

  • Finalize Enclosures Layout
    (to plan for post W2021)

Spring Term

  • Assembling Final Versions of Boards

  • Complete all board mounts

  • Complete all harnesses

  • Complete all enclosures

  • Assemble all items

See full documentation here

Core Team

Name (Term)

Responsibilities

On-Site Capacity

Aashmika (Co-op)

• Assembly of final versions of boards
• Integration into mockup
• ASC VDR

• Remote (Toronto)
• Available on most weekends
• Can possibly take some boards home to work on, during the week

Micah
(Co-op)

• Motor sense validation
• HV testing for mockup
• Enclosures + enclosure layouts

• On Site

James L (School)

• Assembly of final versions of boards
• Telemetry Diagram

• Remote, On Site in February?
• Can do hand soldering, will need equipment

Nita
(Co-op)

• Onboarding
• Acquiring Samples
• Task force for diagram making

• Remote
• Can visit on some weekends, cannot take home equipment (moving)

Liam
(Co-op)

• Onboarding
• BOM Consolidation
• ASC BMS VDR

• Remote
• Probably won’t be in Waterloo, also does not have equipment

Kristen
(Co-op)

• Harnesses?

• On Site
• Grunt work (smile) that requires limited hardware knowledge

...