TEAM: Daphne Lai (Deactivated) Ivan Cao (Deactivated) Jieun Lee Renzo Villanoy

...

Expand
titleThursday, October 29th

JIEUN

  • Deadline for sheet metal: On the outside, can be gathered last (2024 Al) (3-4 mm)

  • Fabric: next steps?

    • Originally have Lovisa if she can go to Ethan & Allen

RENZO

  • Got a 3D printer over the weekend

    • can prototype stuff at home

  • Assembly plans are coming along

    • Working in parallel with Battery box (Micah black)

    • Just the outer fibreglass stuff for now

  • Kristen is planning to purchase soon (click bonds, MDF, and mold stuff)

  • Start researching MDF CNC

IVAN

  • Finish manufacturing plan by October 31st

    • Still catching up on lectures rn

Expand
titleWednesday October 14th

FABRICS (Jieun)

  • Lovisa to look at Ethan Allan offline store

  • Confirmed concept & fabrics

    • Just need to figure out where to get it from

  • Sheila to give new members tasks

FORM FACTOR (Renzo)

  • MDF 20mm thick sheets âś…

    • sheets to be cut down after purchase

      • From forestproducts

  • Brackets for supplier interfacing

  • Click bonds to be supplied through Kristen?

    • Need part names + quantities

  • 3D print started for testing

  • Manufacturing can begin when MDF is delivered

  • To update BOM

MATERIALS (Ivan)

  • Can't use Nomex

    • New foam = Divynice HM80 foam (PVC foam)

      • Sourced from Composites Canada

  • Epoxy resin

    • Amount needed âś…

    • No specific product

    • Aeropoxy PR2032

  • Need mold release

  • Ask Min for sealant tape

Info

All purchases should be within this term

Expand
titleSaturday September 12th (Renzo & Micah Black)

CAD changes

  • Send model numbers and CAD to Renzo (Micah)

  • Raise rear elec enclosure walls at firewall

  • Change 4 fans to 3 and center

  • Move rear elec back to make space for additional row of 4 fans

  • Change holes to vertical slots on support walls and open up sections for wiring

  • Move latch cover away from contactor

  • Move wire openings to top of rear elec divider walls

  • Add clickbond studs to third rear elec bottom panel

  • Fillet corners on rear elec bottom panels

  • Redesign battery module securing brackets with extra vertical support (try to minimize number of fasteners) and do bending calculations

  • Add connection ports to port cover

  • Move port cover in between PCBs

Image AddedImage Added

Expand
titleTuesday September 8th
Image Added

Expand
titleFriday September 4th
Image Added

Expand
titleSaturday August 29th
Image Added

Expand
titleFriday August 21st
Image AddedImage Added

Expand
titleSaturday August 15th
Image AddedImage Added

Expand
titleSaturday August 8th 2020
Image Added

Expand
titleTuesday August 4th 2020
Image Added

Expand
titleWednesday July 29th 2020 Meeting Notes

Updates:

Finalized all materials needed - urethane foam (fibreglass foam core) and epoxy resin.

Message Micah Black about the seal… waiting for a reply.

“Marking” is different from “seal”

Ivan’s break is at 8:30-9:00 pm

Next Steps:

Manufacturing plan for molds.

Expand
titleTuesday July 28th 2020 Meeting Notes

Updates:

Covers for latches - reduce collision with batteries (made if 3D Printing, attached with epoxy)

Added support grid under the base

Added structural ribbing along the edges of the enclosure (epoxy on)

Connection port - 3 inputs, leave a blank slot for now, as we are not sure which ports to model

Seal? - No reply from email, will ask Adrian Micah before Thursday.

Will lay off of front design, don’t want to conflict with dashboard

Fabric - Made group chat with Testing DRI’s to search for fabrics together! Researched cleanliness (hydrophobic/antimicrobial coating or a fabric protector) and padding (sponge foam roll/roll tiles).

3D Printing - fast drying polyurethane with spray paint

Next steps:

Renzo - Create a general list of materials to use and amount. Then send list to Kristen.

...