Cooling System Optimization

Investigation into Cooling System Need

Battery Performance

Dec. 2022

Battery

** Backlogged for now **

Coulomb Counting for Capacity of battery

Initial Research Tickets

  • Explore the different methods in more detail

  • Explore what has been done in the past

  • Explore our current constraints
    • Gather constraints for our use-case

    Battery/Strategy Audits

    • Team individual documentation/code audits to determine “what’s there” and most importantly determine what was achieved before

    Dec. 2022

    Strategy / Battery

    • 1 member assigned to Columb Counting from each team

    • Teams work together on a weekly basis to carry out agile development

    • We iterate as we progress starting with most simple concept

    • Cross verify methods as they get more advanced with expected results

    • Validate with different currents (constant and changing)

    • Explore previously collected data from previous projects

    Battery Module Testing

    Battery/Strategy Audits

    • Team individual documentation/code audits to determine “what’s there” and most importantly determine what was achieved before

    Dec. 2022

    Strategy / Battery

    Battery WIP to explore Micah’s work. (Check out Micha’s GitHub)

    Battery-led development. Strategy available to assist with any tasks.

    Battery Monitoring Dashboard

    Prototyping Phase

    • Designing dashboard, mock-ups, from initial research, competitive analysis

    • Generate “Menu” for Battery team

    Initial Research

    • Generate list of data that is 1) feasible 2) desired and 3) measurable

    Dec. 2022

    Strategy / ~ Battery

    Strategy WIP, will generate “MENU” once term kicks off.

    Solar Array Testing

    Battery Ownership

    • Battery - Gauge interest in leading project

    • Strategy - Find dedicated member to lead project and begin to scope the data collection plan.

    Re-convene with possible owner(s).

    Dec. 2022

    Strategy / ~ Battery

    Priority: Assign a Strategy member to lead. In-person BAY visit to figure out solar cart, measurement tools, logistics, battery involvements, etc.

    Optional requisite: MMPT functionality, test separately and then integrate

    Mimic a measurement this Winter to support the data collection plan.

    Measure every parameter. Angle, date, weather, temp.

    Expected solar energy vs received solar energy.

    Sunny Day

    Complete Strategy ownership - will keep battery in the loop.

    Dec. 2022

    Strategy