Design Projects
Project | Tasks | Estimated Duration | Priority | Leads |
---|
Pedal Board | - Use CAN to communicate with the main system
- Consider using a potentiometer instead of the existing magnetic sensor
- Finish the board design
- Talk with the mechanical team able any board dimension change
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-82 |
---|
|
| 2 Months | High | Kelly, Jenny, Justin
|
Steering Stalk | -
Use CAN to communicate with the main system Transmit analog signal over long wires - Finish the board design
- Make sure the new steering stalk has sufficient mechanical clearance
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-83 |
---|
|
| 2 Months | High | Kelly & Aashmika |
Center Console | - Use CAN to communicate with the main system
- Resign the buttons for greater electromagnetic interference immunity
- Finish the board design
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-84 |
---|
|
| 2 Months | High | Kelly & Liam |
Telemetry | - Find a router and a LTE shield for Telemetry
| 2 Months | Medium | Pei, Felix |
BMS AFE | - Redesign for higher discharge capability and more reliability
Jira Legacy |
---|
server | System JIRA |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-75 |
---|
|
| 2 Months | Medium | Taiping Josh Justin |
BMS Carrier | - Implement a kill switch with greater electromagnetic interference immunity
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-87 |
---|
|
| 2 Months | Medium | Taiping |
BMS Current Sense | - Higher accuracy by using a different ADC
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-86 |
---|
|
| 2 Months | Medium | Taiping & Rishi |
Controller Board | -
Consider using a different microcontrollermicro-controller Won't do
| - | Low | Kelly |
Validation & Integration Projects
Project | Tasks | Estimated Duration | Priority | Leads |
---|
Motor Controller Interface | - Investigate the communication issue with the motor controller
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-60 |
---|
|
| 2 Weeks | Very High | Hanna |
Solar Sense | Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-56 |
---|
|
| 1 Month | Medium | Pei Alicia Cindy |
Power Distribution | - Finish the board bring-up & soldering
- Validation & Integration
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-74 |
---|
|
| 2 Weeks | High | Kelly Justin |
Driver Display | Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-15 |
---|
|
| 1 Month | Medium | Kelly Jessica |
Pre-Charge | Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-73 |
---|
|
| 1 Month | Medium | Hanna Josh Laura |
EV Charger | - Validate the circuits on the bench
- Integration
Jira Legacy |
---|
server | System JIRA |
---|
serverId | 6df7ba0d-c6df-39f5-b19f-bb96d235af5f |
---|
key | HW-71 |
---|
|
| 2 Weeks | Medium | Hanna Justin |
Timelines
Design Projects
Sep 22 - Project Assignment & Research
Sep 29 - Block Diagram & Component Selection & Firmware Integration Discussion
Dec 3 (Unplanned) - Prototyping
Oct 6 - Schematic & PCB Design
Oct 15-19 Midterm
Oct 27 - PCB Review & Order
Nov 3 - PCB Bring-Up & Firmware Support
Nov 17 - Validation
Validation & Integration
Sept 22 - Validation Begins
...
Oct 20 - Begin schematic for revised hardware if needed
Nov 3 - Schematic review, begin layout
Nov 15 - Layout review
Nov 19 - Send PCBs to fab
Nov 26 - Receive PCBs, begin bring up and validation
System Leads
Powertrain - Hanna
- Pre-charge
- Motor Controller Interface
- DC-DC
- Charging
Battery - Taiping
- BMS (Battery Management System)
- Battery pack design
Solar - Pei
- Cells, layout
- MPPT
- Solar Sensing
Interface - Kelly
- Driver Display
- Driver Controls
- Lights
Telemetry - Pei
Infrastructure - Kelly
- Controller Board
- Power distribution
...