titleThe project planning document should contains the following information:
  • Project Team Chart

    • Project DRI & Team

    • Interdependencies

    • Stakeholders

  • Problem Breakdown

    • Background

    • Needs statement

    • Major goals

    • Requirements/Regulations

  • Project Planning Review and Design Kick-off

...

Expand

Project DRI

Project Members

Subteam Lead & PM

Interdependencies & Stakeholders

@Name

Form-factor: @Name

Mtl’s/Mfr/Assem: @Name

Testing/Validation: @Name

Aspect: @Name

Lead: @Name

PM: @Name

Mechanical:

Aerobody: @Name

Hardware:

Light Boards: @Name

Firmware:

Lights Driver: @Name

Problem Breakdown

Background

Expand

Headlights are one of the requirements listed by the American Solar Challenge (however not required for the World Solar Challenge). For MS XIV, the headlight unit will contain two types of lights: Daytime Running Lights (DRL’s) and Front Turn Indicators.

Needs Statement

Expand

i.e A need exists for a headlight unit that meets the DRL (Daytime Running Lights) and front turn signal regulations (ASC) while maintaining good vehicle aerodynamics, minimal energy consumption, and is aesthetically pleasing.

...

Relevant Requirements/Regulations

Headlights are one of the requirements listed by the American Solar Challenge (however not required for the World Solar Challenge). For MS XIV, the headlight unit will contain two types of lights: Daytime Running Lights (DRL’s) and Front Turn Indicators.
Expand

Project Planning Review and Design Kick-off

...