Note |
---|
Will recommend that we email the Scrutineers that review the VDRs to get feedback on our seats and steering wheel, both of which we are designing from scratch. VDR is in progress for seats (~75% ~85% completed). |
Project | Task | Time Allocation | Status | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT |
All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT | ||||||||
Catamaran Cover | Manufacture Molds
| 2 weeks |
| ||||||||
Manufacture Major Battery Box Panels (bottom + side walls + lid)
| 3 weeks |
| |||||||||
Manufacture Internal Parts | 1 week |
| |||||||||
Material Testing
| 1 week |
| |||||||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week |
| |||||||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks |
| |||||||||
External Finish
| TBD |
| |||||||||
Seats | Seats Mock-up (optional) | 1 week |
| ||||||||
Manufacture Seats Flat Panels using the Glass panel
| 2 weeks |
| |||||||||
Manufacture seat supports
| 2 filets 3 weeks + 1 week = 1 filet 2-3 weeks 0 filets 1 week |
| |||||||||
Ballast using using the Glass panel
| 2 weeks |
| |||||||||
Brackets and fastener installation
| 3 weeks |
| |||||||||
Manufacture Seatbacks | 2 weeks + 1 week = 3 weeks |
| |||||||||
Finishing Touches | TBD |
|
...
Name (Term) | Responsibilities | On-site Capacity |
---|---|---|
Renzo (SchoolCo-op) | • Leading manufacturing of catamaran cover | On-site |
Sheila (Co-op)School) | • Leading manufacturing of seats | On-site |
Ali (Co-opSchool) | •Design and integration of Dash | On-site |
Cordelia (Co-opSchool) | • PM for dashboard | On-site for Spring |
Asher (Co-op) | • Leading manufacturing of seats | On-siteRemote |
Kimia (Co-opSchool) | • Design of ballast | RemoteOn-site |
Lovisa (SchoolCo-op) | • PM of trim | Remote |
Jens (School) |
| On-site |
Joy () |
| On-site |
Onboarding Project
Onboarding Project Instructions
...