  1. Verify battery regulations and our pack spec | June 2nd (KOSTUBH)

  2. Assemble Hardware Assembly v7 | June 16th

    1. Materials

      1. Find spot welder

      2. Find thermistors

      3. Find DAQ

    2. DAQ

      1. I/O with PC

      2. header soldering (Donna Kim )

      3. thermistor assembly (Darton Phoebe Luo )

      4. thermistor placement (Module Testing Wiring Schematic - Google Slides)

      5. voltage sense assembly

      6. voltage sense placement

    3. Spot-weld nickel strips

    Debug PSU
  3. Testing procedure | June 30th

    1. Charge/DIscharge Discharge profiles

  4. CAD Module Iteration | July 14th

  5. Build v8 | July 21st

  6. Test | July 28th

  7. TBD

...

Phoebe’s Ongoing to-do list (in order):

  •  Figure out DAQ and thermistor placement
  •  Look into how to attach the thermistors
  •  Figure out what parameters you want to test
    •  Heat on the bus bars

...