Project | Tasks | Estimated Duration | Priority | Leads |
---|---|---|---|---|
Motor Controller Interface |
| 2 Weeks | Very High | Hanna |
Solar Sense |
| 1 Month | Medium | Pei |
Power Distribution |
| 2 Weeks | High | Kelly |
Driver Display |
| 1 Month | Medium | Hanna |
Pre-Charge |
| 1 Month | Medium | Hanna |
EV Charger |
| 2 Weeks | Medium | Hanna |
Timelines
Design Projects
Sep 22 - Project Assignment & Research
Sep 29 - Block Diagram & Component Selection & Firmware Integration Discussion
Oct 6 - Schematic & PCB Design
Oct 15-19 Midterm
Oct 27 - PCB Review & Order
Nov 3 - PCB Bring-Up & Firmware Support
Nov 17 - Validation
Validation & Integration
Sept 22 - Validation Begins
Sept 29 - Most of validation complete, begin to get an idea of if a new rev is required
Oct 6 - Fully complete validation, rework exisiting boards to prototype any new changes
Oct 20: Begin schematic for revised hardware if needed
Nov 3: Schematic review, begin layout
Nov 15: Layout review
Nov 19: Send PCBs to fab
Nov 26: Receive PCBs, begin bring up and validation
System Leads
Powertrain - Hanna
...