Coulomb countingFound fuel guage IC that we might be able to use for main pack, a lot of FW complexity Strategy algo progress basically 0 Decision to be made next Tuesday on which method to pursue, to consider Forest to build 36x1 pack this weekend to support testing of CC + AFE
TelemetryRF implementation is complex and involves dealing with FW drivers, regulations, and interference From strat, we only need accurate SOC every 5 mins for their model, possible to do over radio Baseline is no live data, will be a task but not on the critical path
Battery box board mountingStarted mounts, mostly done with carrier To focus on AFEs since they are most complete To get current sense as close as possible to carrier Figure out HV harnessing and where to place current sense
|