Project

Fall 2023 Sub-Tasks

Deadline

Assignee

Notes

Aux Battery

Finish CAD - Sept 17
Prototype Module - Oct 1
Aux Design Freeze - Oct 17
One module - Oct 20
Aux Enclosure Manufactured - Oct 31
All manufactured - Nov 15

November 30, 2023

Darton

Battery

All modules manufactured - Nov 30

November 30, 2023

Donna + Jenna

BMS

Colomb counting

N/A

HW + FW
Eric + Kostubh

SoC Estimation

Board Mounts

Finish CAD - Sept 16
Design freeze - Sept 22
Prototype - Sept 22
Manufacturing - Sept 30

September 30, 2023

Maggie + Vaibhav

Enclosure

Enclosure Design & Prototyping- Sept 30
Fan Integration - Nov 15
Wire Harnessing - Nov 30

November 30, 2023

Shem + Nicole

PVDRDocument

writing - Sept 30Fraft Completed → Sept 23

September 30, 2023

Owen

Telemetry

Go to FW → contact Mitch (FW lead)

Katherine + FW