Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

The purpose of this confluence page is so that electrical members may review my calculations.

Specifications:

The battery shall be able to energize protected LV systems until the main battery is energized

...

The battery cannot overheat

Voltage:

Nominally 12V, however voltage levels should not be altogether too significant as voltage is further downregulated to logic levels on each individual board.

Electrical Characteristics:

Energy Budget:

To characterize energy capacity, we will group loads into 3 sections:

...

Required (nominal) capacity: 12.83025 Ah

Power Budget:

Load

Description

Power Demand – Typ [W]

Power Demand – Peak [W]

Telemetry

Raspberry Pi

(Assuming switching regulator at 90% efficiency to downregulate 12V to 5V power)

2.5

2.5

Fans

10.2W – Point estimate

10.2W – Point estimate

Contactors

3 Contactors – 3-5A

3.5W – Typical

180W – Initial closing

Emergency LV Power

In case of BPS fault

54.111

130.630W

Horn

7W horn

7

7

Peak power necessary on startup

Telemetry, Contactors, Fans

192.7

Peak power necessary when phase 2 or 3, normal operation

Telemetry, Contactors, Fans

16.2

Power necessary on BPS fault (if no need to re-close contactors):

Fans, Contactors, Emergency LV Power (incl. telemetry), Horn

74.81100

151.33

Peak power necessary on BPS fault (if yes need to re-close contactors):

Telemetry, Fans, Contactors, Emergency LV Power (incl. telemetry) Horn

251.31100

327.83

...

Current – Peak on BPS fault & MPS must be re-opened: 27.32 A

Things to Verify:

  1. Contactor Loads

  2. Horn Loads

    1. Chances of being constant 7W is kind of low? What’s peak current demand?

  3. Telemetry Loads

  4. How long do we need emergency power for on BPS fault?

  5. What’s an acceptable S.F?

...

Will the MPS ever need to be opened again after it has been closed?

Pack Arrangements:

10s1p

10s2p

10s3p

Watt-hours (rated)

120

240

360

Watts

120

240

360

Energy Loads

Persistent loads met?

No

1.65 S.F.

2.47 S.F.

Persistent + 5 mins emergency loads met?

No

1.56 S.F

2.34 S.F.

Power Loads

Typical Phase 2 or 3

7.41 S.F

14.81 S.F.

22.22 S.F.

Peak Startup

No

1.25 S.F.

1.87 S.F.

Typical BPS fault

1.6 S.F.

3.2 S.F.

4.8 S.F.

Peak BPS fault

No

1.59 S.F

2.38 S.F.

Typical BPS Fault & MPS Re-energization

No

No

1.43 S.F.

Peak BPS Fault & MPS Re-energization

No

No

1.1 S.F.

Runtime [hrs]

7.4

15

22

Mass (of cells) [kgs]

1.45

2.90

4.35

Resistance (of cells, nominal) [mOhm]

18

9

6

Conclusions:

  1. It is evident that 10s1p is insufficient to run all aux loads for one race day

  2. 10s2p contains enough energy for one race day and can supply enough power for all loads calculated (if loads are correct), however cannot re-energize the MPS if it is de-energized, must power the LV loads and must be re-energized. This is likely not necessary, as the car has to pull over and fix the BPS fault before continuing, as per regs. The safety factor for capacity is 1.65, which may or may not be sufficient, as thermal effects, parasitic resistances, and future alterations to loads may increase the required capacity.

  3. Please verify if the loads are correct?

Mechanical Characteristics

Thermal Constraints

(TBD)

(Make sure the busbars don’t get so hot that the plastic melts, or that the module can withstand such heat)

...