My plan for tasks in in the tables below.
Front Suspension
Task | Milestones | DRI |
---|---|---|
Hub - FEA, Modifications, Drawings | SolidWorks FEA Training Complete - Jan 18th FEA Set-up Complete - Feb 1st Passing Mesh Convergence - Feb 17th Complete Drawings - March 6th | Michael Hanley |
Spindle - FEA, Modifications, Drawings | Alisa Shirkalina | |
Upright - FEA, Modifications, Drawings | Mackenzie Lui | |
UCA - FEA, Modifications, Drawings | Matthew Scorcia | |
LCA - FEA, Modifications, Drawings | Jasmine Thind | |
Arm Clevis - CAD, FEA, Modifications, Drawings | SolidWorks FEA Training Complete - Jan 18th Motion Analysis - Jan 25th CAD Concept - Feb 1st FEA Set-up Complete - Feb 8th Passing Mesh Convergence - March 8th Complete Drawing - Mar 13th | Wesley Davis |
Shock Clevis - CAD, FEA, Modifications, Drawings | ||
Spec-ing Bearings | Spec Sample Part - Jan 30th | Co-ops |
Spec-ing Rod Ends | Spec Sample Part - Jan 30th | Co-ops |
Spec-ing Dowel Pins | Spec Sample Part - Jan 30th | Co-ops |
Rear Suspension
Task | Milestones | DRI |
---|---|---|
Trailing Arm - Concept | Finalize Geometry - Jan 18th 3D Concept - Feb 1st | Jonathan Xie |
Trailing Arm - Research/CAD/FEA | CAD Concept - Jan 30th FEA Set-up Complete - Feb 1st Passing Mesh Convergence - Feb 17th Complete Drawing - Mar 8th | Winters Xia |
Trailing Arm - Loading Calcs | Side View Calculations - Jan 18th Top View Calculations - Jan 25th | Ted Stager |
Spec-ing Staked Bearings with Tool | Spec Sample Part - Jan 30th | Co-ops |
Steering
Task | Milestones | DRI |
---|---|---|
Finalize Nodal | Complete - Jan 30th | Evan Li |
Rack and Pinion Housing | Implement Steering Stop Stops - Jan 18th Validate Lubrication Required - Jan 25th Implement Lubrication Features - Feb 6th | |
Rack and Pinion Housing Mount - CAD | Parametric Model Training - Jan 16th Create Parametric Model - Jan 23rd CAD Concept - Feb 8th SolidWorks FEA Training Complete - Feb 15th FEA Set-up Complete - Mar 8th Passing Mesh Convergence - Mar 15th Complete Drawings - Mar 22nd | Malcolm Park |
Tie Rod - CAD/FEA | Parametric Model Training - Jan 16th Create Parametric Model - Jan 18th CAD Concept- Feb 8th SolidWorks FEA Training Complete - Feb 15th FEA Set-up Complete - Mar 8th Passing Mesh Convergence - Mar 15th Complete Drawings - Mar 22nd | Sidharth Sreeram |
Steering Arm - CAD/FEA | Parametric Model Training - Jan 16th Create Parametric Model - Jan 23rd CAD Concept- Feb 8th SolidWorks FEA Training Complete - Feb 15th FEA Set-up Complete - Mar 8th Passing Mesh Convergence - Mar 15th Complete Drawings - Mar 22nd | Andy Shen |
System Level Loading Calcs | Validate Gears Stress - Jan 25th Nodal Loading Calcs Complete - Feb 15th | |
Validate Step Steer | Complete - Feb 1st | Shangheethan Prabaharan |
Spec-ing Rod Ends | Spec Sample Part - Mar 1st | Co-ops |
Brakes
Task | Milestones - Date Complete | DRI |
---|---|---|
Final Braking Torque Check | Complete - Jan 30th | Wesley Davis |
Rotors - Front | Find Optimal Rotor Radius - Jan 18th Define Loading Calcs - Jan 23rd Define Rotor Thickness - Jan 25th Research Thermal Considerations - Feb 1st | Katherine Liu Laasya Rajgopal Chantel LeClercq |
Rotors - Rear | ||
Pedal Mechanism | Parametric Model Training - Jan 16th Estimate Pedal Deflection in Degrees - Jan 18th Brake Pad Friction Test - Jan 18th Scotch Yokes and Similar Mechanisms - Jan 23rd Mechanism Synthesis - Feb 8th CAD Concept/Prelim Drawing - Feb 15th SolidWorks FEA Training Complete - Feb 17th FEA Set-up Complete - Mar 8th Passing Mesh Convergence - Mar 22nd Complete Drawings - Mar 29th | 1B Mech Lads |
Caliper Mounting Bracket - Front Nodal/Loading Calcs/CAD/FEA | SolidWorks FEA Training Complete - Jan 18th Find Optimal Caliper Placement - Jan 25th CAD Concept - Feb 1st FEA Set-up Complete - Feb 15th Passing Mesh Convergence - Mar 15th Complete Drawings - Mar 22nd | 1B Mech Lads |
Caliper Mounting Bracket - Rear Nodal/Loading Calcs/CAD/FEA | 1B Mech Lads | |
Parking Brake |
...