Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Project

Task

Time Allocation

Status

Catamaran Cover + Seats

Obtain all materials required for manufacturing the catamaran cover
(MDF, layup consumables)

Finish assembly plan

BOT

Status
colourYellow
titleIn PRogress

All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT

Catamaran Cover

Manufacture Molds

  • Cut and glue MDF

  • Machine molds

  • Sand and prime

2 weeks

Status
titleNot Started

Manufacture Major Battery Box Panels (bottom + side walls + lid)

  • Prep work

  • Make extra for test specimens

3 weeks

Status
titleNot Started

Manufacture Internal Parts
• 3D printing
• Cutting and thermoforming polycarbonate

1 week

Status
colourYellow
titlein progress

Material Testing

  • Deflection test

  • Heat test

  • Adhesive test

1 week

Status
titleNot Started

Dry Run Assembly with Electronics

• Install electronics and battery modules

• Mark part locations

• Test fit catamaran cover into car

→ Will gate electrical

1 week

Status
titleNot Started

  • will require coordination of finished chassis, bottom panel, battery modules

Final Assembly
• Epoxy internal components
• Install electricals

• Permanent mounting of catamaran cover to chassis

2 weeks

Status
titleNot Started

External Finish
• Add fabrics and other cosmetic trim to battery box

Status
titleNice to Have

TBD

Status
titleNot Started

Seats

Seats Mock-up (optional)
• Fabricate and install flat panels in wood to verify seating position, harness pass-thru, visibility, steering wheel and pedal position
• May need to mock-up seatback using flat sheets

1 week

Status
colourGreen
titleDONE

Manufacture Seats Flat Panels using the Glass panel

  • Fabricate all seat pan & seat support flat panels in carbon fibre (either in 1 go or 2 depending on the size of vacuum bag)

  • Bond flat panels to bottom panel/structural elements

2 weeks

Status
titleNot Started

Manufacture seat supports

  • depending on method chosen:

    • 2 built in filets (require small amount of mdf and require producing each seat support separately which is time consuming considering there are 8 of them)

    • 1 built in filet (require producing each seat support separately which is time consuming considering there are 8 of them)

    • 0 built in filets (will be weaker around 1.5-3 times based on research but can manufacture flat pieces 4 supports at a time meaning there will only be 2

weeks + 1 week = 3 weeks
    • rounds of infusion)

2 filets 3 weeks

1 filet 2-3 weeks

0 filets 1 week

Status
titleNot Started

Ballast using using the Glass panel

  • after install of seat pan the measurements and checking to make sure the ballast will hold enough weight/there will enough room

  • begin manufacturing flat panels (glass sheet)

  • install with hinges, lock, and lid

2 weeks

Status
titleNot Started

Brackets and fastener installation

  • order brackets (if VDR approved)

  • order screwsbigheads

  • order fuji/flex locks

  • drill appropriate holes and weld brackets onto chassis

3 weeks

Status
titleNot Started

  • Further purchases are required (brackets approved by EngSoc)

  • fasteners TBD

Manufacture Seatbacks
• Fabricate tooling for non-flat panels (mdf)
• Fabricate non-flat seatback panels
• Install seatbacks into car (as well as seat tabs)

2 weeks + 1 week = 3 weeks

Status
titleNot Started

Finishing Touches
• Fabricate foam padding and cushions and install
• Fabricate and install remaining fabric coverings
• Install harnesses

TBD

Status
titleNot Started

  • These can be done over long term

  • Further purchases are required: fabric

...