Project | Task | Time Allocation | Status | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Catamaran Cover + Seats | Obtain all materials required for manufacturing the catamaran cover Finish assembly plan | BOT |
All MDF for catamaran cover by mid-march, mdf for seats and doors by EOT | ||||||||
Catamaran Cover | Manufacture Molds
| 2 weeks |
| ||||||||
Manufacture Major Battery Box Panels (bottom + side walls + lid)
| 3 weeks |
| |||||||||
Manufacture Internal Parts | 1 week |
| |||||||||
Material Testing
| 1 week |
| |||||||||
Dry Run Assembly with Electronics • Install electronics and battery modules • Mark part locations • Test fit catamaran cover into car → Will gate electrical | 1 week |
| |||||||||
Final Assembly • Permanent mounting of catamaran cover to chassis | 2 weeks |
| |||||||||
External Finish
| TBD |
| |||||||||
Seats | Seats Mock-up (optional) | 1 week |
| ||||||||
Manufacture Seats Flat Panels using the Glass panel
| 2 weeks |
| |||||||||
Manufacture seat supports
| 2 filets 3 weeks 1 filet 2-3 weeks 0 filets 1 week |
| |||||||||
Ballast using using the Glass panel
| 2 weeks |
| |||||||||
Brackets and fastener installation
| 3 weeks |
| |||||||||
Manufacture Seatbacks | 2 weeks + 1 week = 3 weeks |
| |||||||||
Finishing Touches | TBD |
|
...