Project

Goal

OG Date

Date (March)

Priority

Catamaran Cover

Complete manufacturing

3 months

End of May

3 months

End of Sep

Status
colourRed
titleHigh

Seats

Complete manufacturing (plan https://docs.google.com/document/d/1t6-ZhpMnQ-8Mp0LCcsmOvhaA2A8u8Zm8mg8Jn0yAIVg/edit# )

  • testing to confirm design

  • start seat pan manufacturing

  • weld brackets to the chassis

2 months
End of April

2 Months

F21

Status
colourRed
titleHigh

Doors

Complete FULL manufacturing plan (EOT W21)

  • Hinges and Latch need access to A-Plane

  • Latch & Hinges components (2w)

  • Molds & Composites

    • Need manufacturing plan

    • Manufacturing time

** Any Structures changes to hinges need to be communicated

2 months
End of February

Manufacturing Time: 2 months

Commitment for Manufacturing Completion: Mid-F21

Status
colourRed
titleHigh

Trim

Complete detailed design
Started manufacturing plan

  • Currently figuring out headliner

4 months
Fall Term

Trim Integration: 2 months

Status
colourYellow
titleMedium

Dashboard

Complete detailed design
Started manufacturing plan

4 months
Detailed design & Completed Manufacturing Plan: Mid-S21

Manufacturing: 3 months

Integration: 1-2 months

Status
colourRed
titleHigh

...