Weekly Goals
Week | End of Week Goals | Notes |
---|
July 5 - 11 | Chassis: (All done!) Access to Welding Room Finish sanding & assembling jigs (done) Drop off parts for welding Assembly more jigs Welding components onto Chassis
Aero: (Bleeding into week of July 12 - due to booking conflicts with Waterloop) Battery Box: | |
July 12 - 18 | Chassis: Pick up waterjet parts - End of the week Sand chassis, assemble more jigs
Schedule welding in E5 - welding components onto Chassis
Aero: Finish prepping side panel molds - end of the week
Begin material prep for side panels layup
Make a decision if we want to layup both - yes to both
finish side panel molds 3, 4
b bulkheads sand, potentially make blank and machine second mold as well (based on SDC)
Composites: | |
July 19 - 25 | Chassis: Aero: Composites: Battery Box: Purchases: | |
July 26 - Aug 1 | Chassis: Aero: Cure & Demold L. Side panel (Thursday)
Finish sanding R. Side Panel 3,4 molds
Organize prepreg in the freezer adhesive film, prepreg scraps were put into a bin
larger pieces have been collected and stored
Thursday: check remaining quantity of adhesive film for 2nd side panel
Make material list for 2nd Side Panel B-Bulkhead
Composites (Infusion): Battery Box: | Side panels: #3 almost done #4 up to 600
Purchases to be made: NEED TO DO BY END OF WEEK Battery Box: |
| Chassis: Aero: Check 2nd Side panel sanding finish Prepreg & Adhesive Film Inventory (Bay & Conestoga) Reach out to Brian to machine B-bulkhead mold Mackenzie Lui Kyle Justin Lacson (Deactivated) - let Brian know (Tuesday) Begin Material Prep for 2nd Side Panel
Infusion: | Reach out to Multimatic |